5832 N PENFIELD AVE 91367

Certificate Information: 5832 N PENFIELD AVE 91367

Application / Permit
22047-20000-00582
Plan Check / Job No.
B22VN04386
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
ECPC: NEW 20'6" X 33' POOL WITH A 20'6" X 9' SPA . PER LA CITY STD PLAN No. 265
Permit Issued
Issued on 4/25/2022
Issuing Office
Current Status
CofO Issued on 2/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/22/2022 APPLICANT
Assigned to Plan Check Engineer 3/25/2022 LUISANGEL VALENZUELA
Corrections Issued 3/26/2022 LUISANGEL VALENZUELA
Plan Check Approved 4/14/2022 LUISANGEL VALENZUELA
Building Plans Picked Up 4/14/2022 APPLICANT
Issued 4/25/2022 APPLICANT
CofO in Progress 9/22/2022 SEAN HAUPT
CofO in Progress 9/22/2022 SEAN HAUPT
Permit Finaled 2/4/2023 MICHAEL SMITH
CofO Issued 2/4/2023 MICHAEL SMITH
Permit Finaled 2/4/2023 MICHAEL SMITH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/28/2022 LUISANGEL VALENZUELA

Contact Information

Contractor Owner-Builder       ,
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/27/2022 Approved SEAN HAUPT
Gas Piping or Gas Test 4/27/2022 Approved SEAN HAUPT
Gunite 4/27/2022 Not Ready for Inspection SEAN HAUPT
Pre-Gunite 4/27/2022 Not Ready for Inspection SEAN HAUPT
Rough-Electrical 4/27/2022 Approved SEAN HAUPT
Rough-Plumbing 4/27/2022 Approved SEAN HAUPT
Pool Piping 4/28/2022 Not Ready for Inspection SEAN HAUPT
Pre-Gunite 4/28/2022 Approved SEAN HAUPT
Rough-Plumbing 4/28/2022 Not Ready for Inspection SEAN HAUPT
Deputy Shotcrete 5/6/2022 Partial Approval SEAN HAUPT
Grounding or Bonding 6/2/2022 Approved SEAN HAUPT
Enclosure/Fence 6/27/2022 Corrections Issued DAVID SANDOVAL
Enclosure/Fence 6/30/2022 Not Ready for Inspection SEAN HAUPT
Enclosure/Fence 7/12/2022 Approved SEAN HAUPT
Special/Order Compliance 7/12/2022 Corrections Issued SEAN HAUPT
Final 7/22/2022 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 7/22/2022 SGSOV Approved JEFFREY BULL
Pool Equipment Noise Test 7/25/2022 Approved FELIPE PENICHE
Final 9/21/2022 OK to Issue CofO SEAN HAUPT