6723 W COLGATE AVE 90048

Certificate Information: 6723 W COLGATE AVE 90048

Application / Permit
22047-20000-00580
Plan Check / Job No.
B22VN04351
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 29-8" x 15'-0" POOL AND 8'-0" x 8'-0" SPA PER CITY STD. PLAN #268
Permit Issued
Issued on 5/25/2022
Issuing Office
Current Status
CofO Issued on 8/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/22/2022 APPLICANT
Assigned to Plan Check Engineer 3/23/2022 ALFRED RAMIREZ
Corrections Issued 3/23/2022 ALFRED RAMIREZ
Plan Check Approved 5/13/2022 ALFRED RAMIREZ
Building Plans Picked Up 5/18/2022 APPLICANT
Issued 5/25/2022 APPLICANT
CofO in Progress 8/23/2023 DAVID FEILER
Permit Finaled 8/29/2023 DANIEL ORRANTE
CofO Issued 8/29/2023 DANIEL ORRANTE
Permit Finaled 8/29/2023 DANIEL ORRANTE

Permit Application Clearance Information

Construction within easement Cleared 5/10/2022 RIDWAN HARDY

Contact Information

Contractor Intex Design And Construction Inc; Lic. No.: 981718-C53 15021 VENTURA BLVD STE 520      SHERMAN OAKS, CA 91403
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/15/2022 Corrections Issued EVAN COOPER
Excavation/Setback/Form/Re-Bar 7/28/2022 Corrections Issued EVAN COOPER
Pre-Gunite 8/5/2022 Approved EVAN COOPER
Deputy Shotcrete 8/16/2022 Conditional Approval MICHAEL PELHAM
Grounding or Bonding 9/20/2022 Partial Approval EVAN COOPER
Pool/Spa Cover 9/20/2022 Partial Approval EVAN COOPER
Enclosure/Fence 9/26/2022 Not Ready for Inspection EVAN COOPER
Pre-Inspection 9/26/2022 Not Ready for Inspection EVAN COOPER
Pre-Inspection 10/20/2022 Corrections Issued EVAN COOPER
Enclosure/Fence 4/14/2023 Approved JEREMY TODD
Equipment Noise Level 5/16/2023 Approved ZEYDI STEWART
Equipment Noise Level 5/23/2023 Approved ZEYDI STEWART
Excavation/Setback/Form/Re-Bar 6/28/2023 Approved DAVID FEILER
Final 6/28/2023 Corrections Issued DAVID FEILER
SGSOV-Seismic Gas S/O Valve 6/28/2023 SGSOV Not Ready DAVID FEILER
Final 8/2/2023 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 8/2/2023 SGSOV Not Ready ARAM AVEDISIAN
Final 8/15/2023 No Access for Inspection MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 8/15/2023 SGSOV Not Ready MEL KHACHATOURIAN
Final 8/17/2023 OK to Issue CofO MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 8/17/2023 SGSOV Approved MEL KHACHATOURIAN