4532 W GAINSBOROUGH AVE 90027
Certificate Information: 4532 W GAINSBOROUGH AVE 90027
- Application / Permit
- 22047-20000-00417
- Plan Check / Job No.
- B22VN03174
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW (27'-5"X 14'-6") POOL WITH A (5'-0" X 8'-0") SPA AND ATT. 6' TALL WATER FEATURE
- Permit Issued
- Issued on 5/26/2022
- Issuing Office
- Current Status
- CofO Issued on 6/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 3/8/2022 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 3/11/2022 | APPLICANT |
| Applicant returned to address corrections | 4/20/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 5/26/2022 | MOHAMMAD ESMAILI |
| Issued | 5/26/2022 | APPLICANT |
| CofO in Progress | 6/13/2023 | JOSEPH MCGARRY |
| Permit Finaled | 6/17/2023 | DEROLD HAUFF |
| CofO Issued | 6/17/2023 | DEROLD HAUFF |
| Permit Finaled | 6/17/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/8/2022 | MOHAMMAD ESMAILI |
| Miscellaneous | Cleared | 3/14/2022 | MIGUEL GAMBOA |
Contact Information
| Contractor | Aqua Blue Construction Pools And Spas; Lic. No.: 964740-C53 | 23890 COPPER HILL DRIVE #188 VALENCIA, CA 91354 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
| Landscape Architect | Coffee,, Meg Rushing; Lic. No.: LA4747 | 1313 W ALAMEDA AVE BURBANK, CA 91506 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 8/26/2022 | Approved | JOSEPH MCGARRY |
| Grounding or Bonding | 8/26/2022 | Partial Approval | JOSEPH MCGARRY |
| Pool Piping | 8/26/2022 | Approved | JOSEPH MCGARRY |
| Pre-Gunite | 8/26/2022 | Approved | JOSEPH MCGARRY |
| Rough-Electrical | 8/26/2022 | Approved | JOSEPH MCGARRY |
| Deputy Shotcrete | 9/8/2022 | Partial Approval | JOSEPH MCGARRY |
| Pre-Inspection | 10/21/2022 | Partial Approval | JOSEPH MCGARRY |
| Enclosure/Fence | 12/2/2022 | Corrections Issued | JOSEPH MCGARRY |
| Grounding or Bonding | 12/16/2022 | Corrections Issued | RAUL BARAJAS |
| Deck | 1/23/2023 | Approved | JOSEPH MCGARRY |
| Enclosure/Fence | 1/23/2023 | Conditional Approval | JOSEPH MCGARRY |
| Special/Order Compliance | 1/23/2023 | Corrections Issued | JOSEPH MCGARRY |
| Equipment Noise Level | 3/13/2023 | Approved | ZEYDI STEWART |
| Final | 5/4/2023 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Final | 5/4/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 5/4/2023 | SGSOV Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 5/11/2023 | Approved | JOSEPH MCGARRY |
| Enclosure/Fence | 5/11/2023 | Approved | JOSEPH MCGARRY |
| Final | 5/11/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Gas Piping or Gas Test | 5/11/2023 | Approved | JOSEPH MCGARRY |
| Pool/Spa Cover | 5/11/2023 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 5/11/2023 | Approved | JOSEPH MCGARRY |
| Final | 6/8/2023 | OK to Issue CofO | JOSEPH MCGARRY |