2717 S MOTOR AVE 90064

Certificate Information: 2717 S MOTOR AVE 90064

Application / Permit
22047-20000-00381
Plan Check / Job No.
B22VN02869
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 42' X 17' POOL AND 10' X 9' SPA WITH INFINITY EDGE WORK PER ENGINEER
Permit Issued
Issued on 5/18/2022
Issuing Office
Current Status
CofO Issued on 3/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2022 APPLICANT
Assigned to Plan Check Engineer 2/28/2022 DANIEL ABRAMYAN
Corrections Issued 3/1/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 4/13/2022 DANIEL ABRAMYAN
Issued 5/18/2022 APPLICANT
Building Plans Picked Up 5/19/2022 APPLICANT
CofO in Progress 3/15/2024 OGANES TARAKHCHYAN
Permit Finaled 3/15/2024 DANIEL ORRANTE
Permit Finaled 3/15/2024 DANIEL ORRANTE
CofO Issued 3/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pool Piping 10/18/2022 Partial Approval OGANES TARAKHCHYAN
Pre-Gunite 10/18/2022 Approved OGANES TARAKHCHYAN
Deputy Shotcrete 10/28/2022 Partial Approval OGANES TARAKHCHYAN
Gas Piping or Gas Test 1/19/2023 Corrections Issued HERBERT GIRON
Rough-Electrical 1/19/2023 Corrections Issued HERBERT GIRON
Gas Piping or Gas Test 1/23/2023 Approved JEREMY TODD
Pool Piping 1/23/2023 Conditional Approval JEREMY TODD
Enclosure/Fence 7/26/2023 Corrections Issued CLAYTON GRAHAM
Excavation/Setback/Form/Re-Bar 8/11/2023 Not Ready for Inspection CLAYTON GRAHAM
Final 8/11/2023 Not Ready for Inspection CLAYTON GRAHAM
SGSOV-Seismic Gas S/O Valve 8/11/2023 SGSOV Not Ready CLAYTON GRAHAM
Grounding or Bonding 11/8/2023 Corrections Issued OGANES TARAKHCHYAN
Rough-Electrical 11/8/2023 Approved OGANES TARAKHCHYAN
Enclosure/Fence 11/20/2023 Corrections Issued OGANES TARAKHCHYAN
Grounding or Bonding 11/20/2023 Approved OGANES TARAKHCHYAN
Enclosure/Fence 1/4/2024 Corrections Issued OGANES TARAKHCHYAN
Enclosure/Fence 1/16/2024 Not Ready for Inspection MEL KHACHATOURIAN
Enclosure/Fence 2/1/2024 Approved OGANES TARAKHCHYAN
Equipment Noise Level 2/27/2024 Not Ready for Inspection JUAN ESCOTO DELGADO
Equipment Noise Level 2/29/2024 Approved JUAN ESCOTO DELGADO
Final 3/1/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 3/8/2024 Approved OGANES TARAKHCHYAN
Final 3/8/2024 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/8/2024 SGSOV Approved OGANES TARAKHCHYAN
Final 3/15/2024 OK to Issue CofO OGANES TARAKHCHYAN