1608 N AMALFI DR 90272

Certificate Information: 1608 N AMALFI DR 90272

Application / Permit
22047-20000-00377
Plan Check / Job No.
B22VN02818
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW IRREGULAR SHAPED 6'-0" x 16'-0" SPA PER CITY STD. PLAN # 268
Permit Issued
Issued on 4/6/2022
Issuing Office
Current Status
CofO Issued on 4/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/26/2022 APPLICANT
Assigned to Plan Check Engineer 2/28/2022 ALFRED RAMIREZ
Corrections Issued 2/28/2022 ALFRED RAMIREZ
Issued 4/6/2022 APPLICANT
Building Plans Picked Up 4/7/2022 APPLICANT
CofO in Progress 4/21/2023 KEVIN SARGSYAN
Permit Finaled 4/22/2023 DANIEL ORRANTE
CofO Issued 4/22/2023 DANIEL ORRANTE
Permit Finaled 4/22/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/28/2022 ALFRED RAMIREZ
ZA Case Cleared 3/29/2022 MIGUEL GAMBOA
ZA Case Cleared 3/29/2022 MIGUEL GAMBOA

Contact Information

Contractor Mr Solar Construction; Lic. No.: 385622-C53 978 NORTH AMEILA AVE      SAN DIMAS, CA 91773
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/27/2022 Corrections Issued JOHN KIDWELL
Pool Piping 5/27/2022 Partial Approval JOHN KIDWELL
Rough-Electrical 5/27/2022 Partial Approval JOHN KIDWELL
Rough-Plumbing 5/27/2022 Partial Approval JOHN KIDWELL
Deputy Shotcrete 6/7/2022 Conditional Approval JUAN VALENZUELA
Deck 6/21/2022 Approved JUAN VALENZUELA
Pre-Gunite 6/21/2022 Approved JUAN VALENZUELA
Enclosure/Fence 8/15/2022 Corrections Issued KEVIN SARGSYAN
Enclosure/Fence 8/17/2022 Approved JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 1/23/2023 Approved KEVIN SARGSYAN
Final 1/23/2023 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 1/23/2023 SGSOV Not Ready KEVIN SARGSYAN
Final 4/19/2023 Not Ready for Inspection KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/19/2023 SGSOV Approved KEVIN SARGSYAN
Final 4/20/2023 OK to Issue CofO KEVIN SARGSYAN