2660 S KELTON AVE 90064

Certificate Information: 2660 S KELTON AVE 90064

Application / Permit
22047-20000-00346
Plan Check / Job No.
B22VN02674
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW (12'-6" X 28'3") POOL WITH A BAJA SHELF AND AN AUTO POOL COVER.
Permit Issued
Issued on 6/1/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 PETER MOSESIAN
Corrections Issued 2/24/2022 PETER MOSESIAN
Building Plans Picked Up 2/25/2022 APPLICANT
Plan Check Approved 4/1/2022 PETER MOSESIAN
Issued 6/1/2022 APPLICANT
CofO in Progress 4/18/2023 JOHNNY MIRANDA
Permit Finaled 4/18/2023 DANIEL ORRANTE
CofO Issued 4/18/2023 DANIEL ORRANTE
Permit Finaled 4/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Drainage to Storm Drain Cleared 3/30/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 4/4/2022 JOSE HERNANDEZ

Contact Information

Contractor National Pools Inc; Lic. No.: 963509-C53 15439 MONTE ST      SYLMAR, CA 91342
Contractor Taylor Jeremy Landscapes; Lic. No.: 989516-C27 P O BOX 1193      VENICE, CA 90294
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pool Piping 6/15/2022 Approved KEVIN SARGSYAN
Pre-Gunite 6/15/2022 Conditional Approval KEVIN SARGSYAN
Deputy Shotcrete 6/24/2022 Conditional Approval JOHNNY MIRANDA
Deck 2/16/2023 Approved JOHNNY MIRANDA
Enclosure/Fence 3/7/2023 Approved JOHNNY MIRANDA
Pool Equipment Noise Test 3/28/2023 Approved ZEYDI STEWART
Excavation/Setback/Form/Re-Bar 3/30/2023 Approved JESUS RODRIGUEZ
Final 3/30/2023 Corrections Issued JESUS RODRIGUEZ
Pre-Gunite 3/30/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 3/30/2023 SGSOV Approved JESUS RODRIGUEZ
Final 4/17/2023 OK to Issue CofO JOHNNY MIRANDA