13442 W SUNNYVIEW LN 91401
Certificate Information: 13442 W SUNNYVIEW LN 91401
- Application / Permit
- 22047-20000-00334
- Plan Check / Job No.
- B22VN02547
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED 19' X 25' IRREGULAR SHAPED POOL W/ 8'-6" X 8'-6" SPA INSIDE PER STANDARD PLAN #268
- Permit Issued
- Issued on 9/20/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2022 | RAPHAEL ROSAS |
| Corrections Issued | 2/26/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/17/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 6/22/2022 | APPLICANT |
| Plan Check Approved | 9/16/2022 | LAWRENCE QUIRANTE |
| Issued | 9/20/2022 | APPLICANT |
| CofO in Progress | 9/19/2023 | RYAN SALAZAR |
| CofO Issued | 10/24/2023 | RUBEN SALAS |
| Permit Finaled | 10/24/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Metro Rail approval | Cleared | 5/26/2022 | RAPHAEL ROSAS |
| Miscellaneous | Cleared | 5/26/2022 | MIGUEL GAMBOA |
Contact Information
| Contractor | Framework Construction & Remodeling Inc; Lic. No.: 1055261-B | 20720 VENTURA BLVD #270 WOODLAND HILLS, CA 91364 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 2/3/2023 | Approved | RYAN SALAZAR |
| Deputy Shotcrete | 2/6/2023 | Conditional Approval | JOHN COLEMAN |
| Pool Equipment Noise Test | 4/24/2023 | Not Ready for Inspection | ALFREDO FLORES |
| Enclosure/Fence | 7/26/2023 | Corrections Issued | ROBERT GOLD |
| Enclosure/Fence | 7/31/2023 | Approved | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 8/11/2023 | Approved | RYAN SALAZAR |
| Final | 8/11/2023 | Corrections Issued | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 8/11/2023 | SGSOV Approved | RYAN SALAZAR |
| Pool Equipment Noise Test | 8/17/2023 | Approved | FELIPE PENICHE |
| Special/Order Compliance | 9/14/2023 | Approved | RYAN SALAZAR |
| Final | 9/18/2023 | OK to Issue CofO | RYAN SALAZAR |