8500 N CAPISTRANO AVE 91304
Certificate Information: 8500 N CAPISTRANO AVE 91304
- Application / Permit
- 22047-20000-00330
- Plan Check / Job No.
- B22VN02477
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 32' X 17' POOL WITH 7' X 7' SPA PER LA CITY STANDARD PLAN #268 AND ENGINEERING DETAILS 208, 400-85
- Permit Issued
- Issued on 8/10/2023
- Issuing Office
- Current Status
- CofO Issued on 4/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 2/17/2022 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 3/30/2022 | DANIEL ABRAMYAN |
| Building Plans Picked Up | 6/7/2022 | APPLICANT |
| Applicant returned to address corrections | 9/20/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 4/18/2023 | RAMA DABADGE |
| Issued | 8/10/2023 | APPLICANT |
| CofO in Progress | 4/16/2024 | JEFFREY HARTLINE |
| Permit Finaled | 4/24/2024 | JOHN JANSON |
| CofO Issued | 4/24/2024 | JOHN JANSON |
| Permit Finaled | 4/24/2024 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/17/2022 | DANIEL ABRAMYAN |
Contact Information
| Contractor | Mr Carlos Pools And Construction Inc; Lic. No.: 385622-C53 | 978 NORTH AMEILA AVE SAN DIMAS, CA 91773 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grounding or Bonding | 12/4/2023 | Approved | JEFFREY HARTLINE |
| Enclosure/Fence | 1/4/2024 | Corrections Issued | JEFFREY HARTLINE |
| Enclosure/Fence | 1/10/2024 | Approved | JEFFREY HARTLINE |
| Pool Equipment Noise Test | 1/25/2024 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 1/26/2024 | Approved | JEFFREY HARTLINE |
| Final | 1/26/2024 | Corrections Issued | JEFFREY HARTLINE |
| Pre-Gunite | 1/26/2024 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 1/26/2024 | SGSOV Approved | JEFFREY HARTLINE |
| Final | 4/16/2024 | OK to Issue CofO | JEFFREY HARTLINE |