10413 N CEDROS AVE 91345

Certificate Information: 10413 N CEDROS AVE 91345

Application / Permit
22047-20000-00298
Plan Check / Job No.
B22VN02299
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 30'-0" x 13'-0" POOL WITH 6'-0" x 10'-0" SPA PER LA CITY STANDARD PLAN# 268 AND ENGINEERING DETAIL# 271-60.
Permit Issued
Issued on 3/25/2022
Issuing Office
Current Status
CofO Issued on 3/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/14/2022 APPLICANT
Assigned to Plan Check Engineer 2/15/2022 SARKIS HARABEDIAN
Corrections Issued 2/15/2022 SARKIS HARABEDIAN
Applicant returned to address corrections 3/2/2022 SARKIS HARABEDIAN
Plan Check Approved 3/16/2022 SARKIS HARABEDIAN
Building Plans Picked Up 3/17/2022 APPLICANT
Issued 3/25/2022 APPLICANT
CofO in Progress 2/24/2023 JENNIFER RABUCHIN
CofO Issued 3/7/2023 MICHAEL SMITH
Permit Finaled 3/7/2023 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 3/4/2022 WALTER RAMIREZ
Construction within easement Cleared 3/4/2022 WALTER RAMIREZ

Contact Information

Contractor Noga Pool And Spa Inc; Lic. No.: 946647-C53 5739 KANAN ROAD #639      AGOURA HILLS, CA 91301
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 3/31/2022 Approved JENNIFER RABUCHIN
Deputy Shotcrete 4/1/2022 Partial Inspection JENNIFER RABUCHIN
Deck 4/18/2022 Corrections Issued JENNIFER RABUCHIN
Grounding or Bonding 4/18/2022 Corrections Issued JENNIFER RABUCHIN
Deck 4/20/2022 Approved JENNIFER RABUCHIN
Grounding or Bonding 4/20/2022 Approved JENNIFER RABUCHIN
Enclosure/Fence 5/25/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/25/2022 SGSOV Not Ready JENNIFER RABUCHIN
Equipment Noise Level 9/12/2022 No Access for Inspection FELIPE PENICHE
Excavation/Setback/Form/Re-Bar 9/14/2022 Approved JENNIFER RABUCHIN
Final 9/14/2022 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/14/2022 SGSOV Not Ready JENNIFER RABUCHIN
Equipment Noise Level 9/19/2022 Approved FELIPE PENICHE
Final 2/23/2023 OK to Issue CofO JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/23/2023 SGSOV Approved JENNIFER RABUCHIN