4509 N RADFORD AVE 91607
Certificate Information: 4509 N RADFORD AVE 91607
- Application / Permit
- 22047-20000-00261
- Plan Check / Job No.
- B22VN02070
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 13'6" X 19' SHOTCRETE POOL 5'5" DEEP WITH A 3' RAISED BOND BEAM AND FIRE FEATURE ON TOP OF THE BOND BEAM PER ENGINEER AND LA CITY STANDARD PLAN #268
- Permit Issued
- Issued on 3/18/2022
- Issuing Office
- Current Status
- CofO Issued on 10/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 2/10/2022 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 3/16/2022 | DANIEL ABRAMYAN |
| Issued | 3/18/2022 | APPLICANT |
| Building Plans Picked Up | 3/24/2022 | APPLICANT |
| CofO in Progress | 9/20/2022 | THOMAS FINNILA |
| CofO Issued | 10/14/2022 | MICHAEL SMITH |
| Permit Finaled | 10/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Pool Logic La; Lic. No.: 1053685-C53 | 1276 E COLORADO BLVD PASADENA, CA 91106 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 4/14/2022 | Corrections Issued | THOMAS FINNILA |
| Pre-Gunite | 4/27/2022 | Corrections Issued | ARAM AVEDISIAN |
| Pre-Gunite | 5/13/2022 | Approved | THOMAS FINNILA |
| Enclosure/Fence | 7/25/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 8/2/2022 | SGSOV Not Ready | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 8/8/2022 | Approved | THOMAS FINNILA |
| Final | 8/8/2022 | Corrections Issued | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 8/8/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Final | 8/12/2022 | Corrections Issued | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 8/12/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Final | 9/6/2022 | Corrections Issued | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Approved | CALEB MEISTER |
| Pre-Inspection | 9/12/2022 | Approved | THOMAS FINNILA |
| Final | 9/19/2022 | OK to Issue CofO | THOMAS FINNILA |