7045 N JELLICO AVE 91406
Certificate Information: 7045 N JELLICO AVE 91406
- Application / Permit
- 22047-20000-00221
- Plan Check / Job No.
- B22VN01699
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- *EPLAN* NEW POOL (17' X 35') AND SPA (7' X 7') PER STD PLAN # 268. Install filtration and heating equipment. Install gas and electric to equipment and lights.
- Permit Issued
- Issued on 6/17/2022
- Issuing Office
- Current Status
- CofO Issued on 4/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2022 | VIVIAN LAO |
| Corrections Issued | 2/10/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 3/1/2022 | VIVIAN LAO |
| Plan Check Approved | 5/26/2022 | VIVIAN LAO |
| Issued | 6/17/2022 | APPLICANT |
| CofO in Progress | 4/21/2023 | SEAN HAUPT |
| Permit Finaled | 4/25/2023 | MICHAEL SMITH |
| CofO Issued | 4/25/2023 | MICHAEL SMITH |
| Permit Finaled | 4/25/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction within easement | Cleared | 5/23/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Swimming Pool & Spa Surgeon; Lic. No.: 466383-C53 | 4685 RUNWAY STREET UNIT P SIMI VALLEY, CA 93063 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/24/2022 | Approved | SEAN HAUPT |
| Pool Piping | 10/24/2022 | Approved | SEAN HAUPT |
| Pre-Gunite | 10/24/2022 | Approved | SEAN HAUPT |
| Rough-Electrical | 10/24/2022 | Approved | SEAN HAUPT |
| Deputy Shotcrete | 11/15/2022 | Conditional Approval | MORRIS JACKSON |
| Grounding or Bonding | 12/12/2022 | Conditional Approval | JON MCHUGH |
| Grounding or Bonding | 12/28/2022 | Approved | JON MCHUGH |
| Enclosure/Fence | 3/8/2023 | Approved | SEAN HAUPT |
| Equipment Noise Level | 4/3/2023 | Approved | FELIPE PENICHE |
| Final | 4/10/2023 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 4/10/2023 | SGSOV Approved | SEAN HAUPT |
| Final | 4/20/2023 | OK to Issue CofO | SEAN HAUPT |