1000 N CASIANO ROAD 90049

Certificate Information: 1000 N CASIANO ROAD 90049

Application / Permit
22047-20000-00210
Plan Check / Job No.
B22VN01608
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 30'-0" X 15'-0" POOL WITH 6' X 6.5' SPA PER LA CITY STANDARD PLAN #268 AND SUPPLEMENTAL DETAIL #672, 220-60
Permit Issued
Issued on 6/29/2022
Issuing Office
Current Status
CofO Issued on 6/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2022 APPLICANT
Assigned to Plan Check Engineer 2/4/2022 JESSE ARELLANO
Corrections Issued 2/4/2022 JESSE ARELLANO
Applicant returned to address corrections 6/28/2022 JESSE ARELLANO
Issued 6/29/2022 APPLICANT
Building Plans Picked Up 7/15/2022 APPLICANT
CofO in Progress 6/7/2023 CARLOS MATAMOROS
Permit Finaled 6/13/2023 DANIEL ORRANTE
CofO Issued 6/13/2023 DANIEL ORRANTE
Permit Finaled 6/13/2023 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 4/1/2022 RIDWAN HARDY
Construction within easement Cleared 4/1/2022 RIDWAN HARDY

Contact Information

Contractor Intex Design And Construction Inc; Lic. No.: 981718-C53 15021 VENTURA BLVD STE 520      SHERMAN OAKS, CA 91403
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 12/15/2022 Approved CARLOS MATAMOROS
Grounding or Bonding 12/15/2022 Approved CARLOS MATAMOROS
Pool Piping 12/15/2022 Approved CARLOS MATAMOROS
Pre-Gunite 12/15/2022 Approved CARLOS MATAMOROS
Rough-Electrical 12/15/2022 Approved CARLOS MATAMOROS
Deputy Shotcrete 12/23/2022 Conditional Approval MICHAEL PELHAM
Deck 4/7/2023 Approved CARLOS MATAMOROS
Grounding or Bonding 4/7/2023 Approved CARLOS MATAMOROS
Enclosure/Fence 5/3/2023 Approved CARLOS MATAMOROS
Equipment Noise Level 5/16/2023 Not Ready for Inspection ZEYDI STEWART
Equipment Noise Level 5/23/2023 Approved ZEYDI STEWART
ELECTRICAL-Final 5/25/2023 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 5/25/2023 Approved CARLOS MATAMOROS
Final 5/25/2023 Partial Approval CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 5/25/2023 SGSOV Approved CARLOS MATAMOROS
Final 6/7/2023 OK to Issue CofO CARLOS MATAMOROS