15120 W OTSEGO ST 91403
Certificate Information: 15120 W OTSEGO ST 91403
- Application / Permit
- 22047-20000-00197
- Plan Check / Job No.
- B22VN01501
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 31'x 17' POOL AND 7' x 7' SPA. PER LA CITY STD PLAN No. 268
- Permit Issued
- Issued on 5/4/2022
- Issuing Office
- Current Status
- CofO Issued on 7/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 2/3/2022 | LUISANGEL VALENZUELA |
| Plan Check Approved | 4/19/2022 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 4/19/2022 | APPLICANT |
| Issued | 5/4/2022 | APPLICANT |
| CofO in Progress | 7/14/2025 | JACK KARGODORIAN |
| Permit Finaled | 7/30/2025 | RUBEN SALAS |
| CofO Issued | 7/30/2025 | RUBEN SALAS |
| Permit Finaled | 7/30/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/18/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/18/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Aquamarine Pool Construction; Lic. No.: 922370-C53 | 13312 RANCHERO ROAD #499 OAK HILLS, CA 92344 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grounding or Bonding | 5/31/2022 | Partial Approval | JACK KARGODORIAN |
| Pool Piping | 5/31/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Pre-Gunite | 5/31/2022 | Corrections Issued | JACK KARGODORIAN |
| Rough-Electrical | 5/31/2022 | Corrections Issued | JACK KARGODORIAN |
| Rough-Plumbing | 5/31/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Pre-Gunite | 6/22/2022 | Corrections Issued | JACK KARGODORIAN |
| Pre-Gunite | 6/29/2022 | Approved | JACK KARGODORIAN |
| Deputy Shotcrete | 7/27/2022 | Approved | JACK KARGODORIAN |
| Deck | 10/27/2022 | Approved | CALEB MEISTER |
| Grounding or Bonding | 10/27/2022 | Approved | CALEB MEISTER |
| Enclosure/Fence | 12/29/2022 | No Access for Inspection | THOMAS FINNILA |
| Enclosure/Fence | 1/6/2023 | No Access for Inspection | JOHN COLEMAN |
| Enclosure/Fence | 1/13/2023 | Corrections Issued | THOMAS FINNILA |
| Enclosure/Fence | 2/9/2023 | Corrections Issued | THOMAS FINNILA |
| Enclosure/Fence | 3/17/2023 | Approved | THOMAS FINNILA |
| Pool Equipment Noise Test | 6/21/2023 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 8/2/2023 | No Access for Inspection | THOMAS FINNILA |
| Final | 8/2/2023 | No Access for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 8/2/2023 | SGSOV Not Ready | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 9/14/2023 | Approved | THOMAS FINNILA |
| Final | 9/14/2023 | Corrections Issued | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 9/14/2023 | SGSOV Approved | THOMAS FINNILA |
| Final | 9/28/2023 | OK to Issue CofO | THOMAS FINNILA |