109 S CARMELINA AVE 90049
Certificate Information: 109 S CARMELINA AVE 90049
- Application / Permit
- 22047-20000-00111
- Plan Check / Job No.
- B22VN00879
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 26' X 12' FIBERGLASS SWIMMING POOL AND 8'-6" X 9'-8" SPA PER ICC
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Current Status
- CofO Issued on 4/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 1/30/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 3/8/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/10/2022 | APPLICANT |
| Issued | 3/17/2022 | APPLICANT |
| CofO in Progress | 3/29/2023 | OGANES TARAKHCHYAN |
| Permit Finaled | 4/12/2023 | DANIEL ORRANTE |
| CofO Issued | 4/12/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/12/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/30/2022 | JEROME MAGAT PALMA |
Contact Information
| Contractor | S & S Pools Inc; Lic. No.: 1073138-C53 | 14173 ASTORIA STREET SYLMAR, CA 91324 |
| Engineer | Poindexter,, Donald Robert; Lic. No.: C24420 | 4119 TRINITY DRIVE SANTA ROSA, CA 95405 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 6/8/2022 | Corrections Issued | JUAN VALENZUELA |
| Rough-Electrical | 6/8/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Rough-Plumbing | 6/8/2022 | Partial Approval | JUAN VALENZUELA |
| Gas Piping or Gas Test | 6/10/2022 | Approved | JOHN KIDWELL |
| Rough-Electrical | 6/10/2022 | Approved | JOHN KIDWELL |
| Rough-Plumbing | 6/10/2022 | Approved | JOHN KIDWELL |
| Pool Piping | 7/1/2022 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 7/7/2022 | Not Ready for Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 8/1/2022 | Approved | ANDREW NAVE |
| Enclosure/Fence | 9/9/2022 | Corrections Issued | KEVIN SARGSYAN |
| Gas Piping or Gas Test | 9/9/2022 | Corrections Issued | KEVIN SARGSYAN |
| Enclosure/Fence | 9/16/2022 | Corrections Issued | JUAN VALENZUELA |
| Enclosure/Fence | 11/2/2022 | Corrections Issued | KEVIN SARGSYAN |
| Enclosure/Fence | 11/7/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Enclosure/Fence | 11/9/2022 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 11/9/2022 | Approved | KEVIN SARGSYAN |
| Gas Piping or Gas Test | 11/16/2022 | Approved | KEVIN SARGSYAN |
| Final | 3/1/2023 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Gunite | 3/1/2023 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 3/1/2023 | SGSOV Not Ready | KEVIN SARGSYAN |
| Final | 3/7/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 3/7/2023 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Final | 3/10/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 3/10/2023 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Final | 3/23/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 3/23/2023 | SGSOV Approved | OGANES TARAKHCHYAN |
| Equipment Noise Level | 3/24/2023 | Approved | JAMES VORHIS |
| Equipment Noise Level | 3/28/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Final | 3/28/2023 | Partial Approval | OGANES TARAKHCHYAN |