109 S CARMELINA AVE 90049

Certificate Information: 109 S CARMELINA AVE 90049

Application / Permit
22047-20000-00111
Plan Check / Job No.
B22VN00879
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 26' X 12' FIBERGLASS SWIMMING POOL AND 8'-6" X 9'-8" SPA PER ICC
Permit Issued
Issued on 3/17/2022
Issuing Office
Current Status
CofO Issued on 4/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/19/2022 APPLICANT
Assigned to Plan Check Engineer 1/28/2022 JEROME MAGAT PALMA
Corrections Issued 1/30/2022 JEROME MAGAT PALMA
Plan Check Approved 3/8/2022 JEROME MAGAT PALMA
Building Plans Picked Up 3/10/2022 APPLICANT
Issued 3/17/2022 APPLICANT
CofO in Progress 3/29/2023 OGANES TARAKHCHYAN
Permit Finaled 4/12/2023 DANIEL ORRANTE
CofO Issued 4/12/2023 DANIEL ORRANTE
Permit Finaled 4/12/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/30/2022 JEROME MAGAT PALMA

Contact Information

Contractor S & S Pools Inc; Lic. No.: 1073138-C53 14173 ASTORIA STREET      SYLMAR, CA 91324
Engineer Poindexter,, Donald Robert; Lic. No.: C24420 4119 TRINITY DRIVE      SANTA ROSA, CA 95405

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 6/8/2022 Corrections Issued JUAN VALENZUELA
Rough-Electrical 6/8/2022 Not Ready for Inspection JUAN VALENZUELA
Rough-Plumbing 6/8/2022 Partial Approval JUAN VALENZUELA
Gas Piping or Gas Test 6/10/2022 Approved JOHN KIDWELL
Rough-Electrical 6/10/2022 Approved JOHN KIDWELL
Rough-Plumbing 6/10/2022 Approved JOHN KIDWELL
Pool Piping 7/1/2022 Approved JUAN VALENZUELA
ELECTRICAL-Final 7/7/2022 Not Ready for Inspection MICHAEL PELHAM
Special/Order Compliance 8/1/2022 Approved ANDREW NAVE
Enclosure/Fence 9/9/2022 Corrections Issued KEVIN SARGSYAN
Gas Piping or Gas Test 9/9/2022 Corrections Issued KEVIN SARGSYAN
Enclosure/Fence 9/16/2022 Corrections Issued JUAN VALENZUELA
Enclosure/Fence 11/2/2022 Corrections Issued KEVIN SARGSYAN
Enclosure/Fence 11/7/2022 Not Ready for Inspection KEVIN SARGSYAN
Enclosure/Fence 11/9/2022 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 11/9/2022 Approved KEVIN SARGSYAN
Gas Piping or Gas Test 11/16/2022 Approved KEVIN SARGSYAN
Final 3/1/2023 Corrections Issued KEVIN SARGSYAN
Pre-Gunite 3/1/2023 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/1/2023 SGSOV Not Ready KEVIN SARGSYAN
Final 3/7/2023 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/7/2023 SGSOV Not Ready OGANES TARAKHCHYAN
Final 3/10/2023 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/10/2023 SGSOV Not Ready OGANES TARAKHCHYAN
Final 3/23/2023 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/23/2023 SGSOV Approved OGANES TARAKHCHYAN
Equipment Noise Level 3/24/2023 Approved JAMES VORHIS
Equipment Noise Level 3/28/2023 Approved AGUSTIN ALVAREZMORALES
Final 3/28/2023 Partial Approval OGANES TARAKHCHYAN