3585 W BEVERLY GLEN TER 91403

Certificate Information: 3585 W BEVERLY GLEN TER 91403

Application / Permit
22047-20000-00092
Plan Check / Job No.
B22VN00626
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL W/INFINITY EDGE ON CAISSONS & GRADE BEAMS
Permit Issued
Issued on 5/24/2022
Issuing Office
Current Status
CofO Issued on 3/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/18/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 KHEDER ALRAZAA
Corrections Issued 2/23/2022 KHEDER ALRAZAA
Quality Review Completed 3/3/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 3/7/2022 APPLICANT
Plan Check Approved 5/24/2022 KHEDER ALRAZAA
Issued 5/24/2022 APPLICANT
CofO in Progress 2/14/2025 JACK KARGODORIAN
Permit Finaled 3/13/2025 RUBEN SALAS
CofO Issued 3/13/2025 RUBEN SALAS
Permit Finaled 3/13/2025 RUBEN SALAS

Permit Application Clearance Information

Specific Plan Cleared 5/6/2022 OLGA AYALA
Grading Pre-Inspection Cleared 5/24/2022 KHEDER ALRAZAA

Contact Information

Contractor Artech Construction; Lic. No.: 848955-B 1136 N-KENTER AVENUE      LOS ANGELES, CA 90049
Engineer Shniderman,, Jason Bernard; Lic. No.: C20524 16000 SHERMAN WAY #234      VAN NUYS, CA 91607
Engineer Shubeck,, Christopher Robert; Lic. No.: C66775 23705 VANOWEN ST 101      WEST HILLS, CA 91307

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/4/2022 Approved JACK KARGODORIAN
Deputy Other (see comments) 8/8/2022 Partial Approval JACK KARGODORIAN
Deputy Other (see comments) 8/22/2022 Partial Approval JACK KARGODORIAN
Pre-Gunite 9/15/2022 Approved JACK KARGODORIAN
Deputy Other (see comments) 9/19/2022 Partial Approval JACK KARGODORIAN
Grounding or Bonding 10/12/2022 Partial Approval THOMAS FINNILA
Gunite 10/12/2022 Approved THOMAS FINNILA
Deputy Shotcrete 10/14/2022 Conditional Approval THOMAS FINNILA
Enclosure/Fence 12/5/2022 Approved THOMAS FINNILA
Final 2/3/2023 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 2/3/2023 SGSOV Approved JUAN VALENZUELA
Equipment Noise Level 2/8/2023 Approved FELIPE PENICHE
Final 2/13/2023 Corrections Issued THOMAS FINNILA
Final 7/12/2023 OK to Issue CofO THOMAS FINNILA