956 S MUIRFIELD ROAD 90019
Certificate Information: 956 S MUIRFIELD ROAD 90019
- Application / Permit
- 22047-20000-00060
- Plan Check / Job No.
- B22VN00410
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 14 X 32 POOL WITH A 6 X 6 SPA INSIDE THE POOL SHELL PER ENGINEERING
- Permit Issued
- Issued on 2/3/2022
- Issuing Office
- Current Status
- CofO Issued on 1/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2022 | COLIN LOREDO |
| Plan Check Approved | 2/3/2022 | COLIN LOREDO |
| Issued | 2/3/2022 | APPLICANT |
| CofO in Progress | 10/19/2022 | JEFFREY MEAD |
| Permit Finaled | 1/21/2023 | DEROLD HAUFF |
| CofO Issued | 1/21/2023 | DEROLD HAUFF |
| Permit Finaled | 1/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Avanti Pools Inc; Lic. No.: 772516-C53 | 8138 ORION AVE VAN NUYS, CA 91406 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 3/18/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Pre-Gunite | 3/21/2022 | No Access for Inspection | CRAIG DAVIS |
| Pool Piping | 3/22/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Pre-Gunite | 3/23/2022 | Conditional Approval | CRAIG DAVIS |
| Deck | 4/13/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Gas Piping or Gas Test | 4/13/2022 | Partial Approval | STUART CHAPMAN |
| Grounding or Bonding | 4/13/2022 | Corrections Issued | STUART CHAPMAN |
| Deck | 5/11/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Enclosure/Fence | 5/11/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Grounding or Bonding | 5/11/2022 | Approved | SHAVONNE ESPINOZA |
| Deck | 5/25/2022 | Not Ready for Inspection | RUBEN SALAS |
| Enclosure/Fence | 5/25/2022 | Partial Inspection | RUBEN SALAS |
| Enclosure/Fence | 6/22/2022 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 7/19/2022 | Approved | JEFFREY MEAD |
| Final | 7/19/2022 | Partial Approval | JEFFREY MEAD |
| Pool Equipment Noise Test | 7/19/2022 | Approved | ROBERT CHAVEZ |
| Pre-Gunite | 7/19/2022 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 7/19/2022 | SGSOV Gas Company | JEFFREY MEAD |
| Final | 7/27/2022 | No Access for Inspection | JEFFREY MEAD |
| Final | 8/4/2022 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Final | 8/11/2022 | Approved | JEFFREY MEAD |
| Final | 8/11/2022 | Corrections Issued | JEFFREY MEAD |
| Final | 10/18/2022 | OK to Issue CofO | JEFFREY MEAD |