13627 W CHANDLER BLVD 91401
Certificate Information: 13627 W CHANDLER BLVD 91401
- Application / Permit
- 22047-20000-00031
- Plan Check / Job No.
- B22VN00226
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 22'-6" X 14'-0" POOL WITH 6' X 12' SPA. PER LA STD PLAN 268
- Permit Issued
- Issued on 1/31/2022
- Issuing Office
- Current Status
- CofO Issued on 8/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2022 | COLIN LOREDO |
| Corrections Issued | 1/12/2022 | COLIN LOREDO |
| Plan Check Approved | 1/12/2022 | COLIN LOREDO |
| Building Plans Picked Up | 1/13/2022 | APPLICANT |
| Issued | 1/31/2022 | APPLICANT |
| CofO in Progress | 8/18/2022 | RICHARD DOCKUS |
| Permit Finaled | 8/27/2022 | DEROLD HAUFF |
| CofO Issued | 8/27/2022 | DEROLD HAUFF |
| Permit Finaled | 8/27/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 3/7/2022 | Approved | RICHARD DOCKUS |
| Deputy Shotcrete | 3/22/2022 | Approved | RICHARD DOCKUS |
| Grounding or Bonding | 4/15/2022 | Approved | RICHARD DOCKUS |
| Grounding or Bonding | 5/25/2022 | Approved | RICHARD DOCKUS |
| Enclosure/Fence | 6/8/2022 | Corrections Issued | RICHARD DOCKUS |
| Enclosure/Fence | 6/10/2022 | Approved | RICHARD DOCKUS |
| Pool Equipment Noise Test | 6/28/2022 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 6/29/2022 | Approved | RICHARD DOCKUS |
| Final | 6/29/2022 | Corrections Issued | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 6/29/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Final | 8/1/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 8/1/2022 | SGSOV Approved | RICHARD DOCKUS |
| Final | 8/17/2022 | OK to Issue CofO | RICHARD DOCKUS |