417 N KENTER AVE 90049
Certificate Information: 417 N KENTER AVE 90049
- Application / Permit
- 22047-20000-00007
- Plan Check / Job No.
- B22VN00078
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 15' X 37' POOL WITH A 5' X 15' SPA.
- Permit Issued
- Issued on 3/7/2022
- Issuing Office
- Current Status
- CofO Issued on 11/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2022 | JAD BASMA |
| Corrections Issued | 1/6/2022 | JAD BASMA |
| Applicant returned to address corrections | 2/10/2022 | OMAR GARNICA |
| Building Plans Picked Up | 2/14/2022 | APPLICANT |
| Plan Check Approved | 2/18/2022 | MOHAMMAD ESMAILI |
| Issued | 3/7/2022 | APPLICANT |
| CofO in Progress | 10/7/2022 | JUAN VALENZUELA |
| CofO in Progress | 10/13/2022 | JUAN VALENZUELA |
| Permit Finaled | 11/3/2022 | DANIEL ORRANTE |
| CofO Issued | 11/3/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/3/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/6/2022 | JAD BASMA |
| Construction near power lines | Cleared | 2/15/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Agam Pool And Spa Inc; Lic. No.: 993464-C53 | 12940 ADDISON ST SHERMAN OAKS, CA 91423 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/15/2022 | Approved | ANDREW NAVE |
| Pool Piping | 3/15/2022 | Approved | ANDREW NAVE |
| Pre-Gunite | 3/15/2022 | Approved | ANDREW NAVE |
| Special/Order Compliance | 3/15/2022 | Partial Inspection | PATRICK QUALEY |
| Deck | 6/29/2022 | Approved | JUAN VALENZUELA |
| Enclosure/Fence | 6/29/2022 | Approved | JUAN VALENZUELA |
| Grounding or Bonding | 6/29/2022 | Approved | JUAN VALENZUELA |
| Pool Equipment Noise Test | 7/12/2022 | Approved | JAMES VORHIS |
| Final | 7/19/2022 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 7/19/2022 | SGSOV Not Ready | KEVIN SARGSYAN |
| Final | 8/22/2022 | Partial Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 8/22/2022 | SGSOV Not Ready | JUAN VALENZUELA |
| Final | 8/26/2022 | Conditional Approval | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 8/26/2022 | SGSOV Approved | JUAN VALENZUELA |
| Final | 10/12/2022 | OK to Issue CofO | JUAN VALENZUELA |