130 S KENTER AVE 90049

Certificate Information: 130 S KENTER AVE 90049

Application / Permit
22047-10001-00577
Plan Check / Job No.
B22VN18453
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
supp tp 22047-20000-00577 to recheck lost plans RECONSTRUCTION OF EXISTING POOL WALL AND NEW SPA . THE NEW POOL AND SPA WILL BE 551 SF. A 6 FEET HIGH FENCE ENCOMPASSES THE ENTIRE PROPERTY.
Permit Issued
Issued on 9/12/2023
Issuing Office
Current Status
CofO in Progress on 2/20/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/16/2022 APPLICANT
Assigned to Plan Check Engineer 12/16/2022 ALFREDO JARA
Corrections Issued 12/19/2022 ALFREDO JARA
Applicant returned to address corrections 1/26/2023 JOSEPH RAFOLS
Applicant returned to address corrections 8/22/2023 JOSEPH RAFOLS
Plan Check Approved 9/8/2023 JOSEPH RAFOLS
Issued 9/12/2023 APPLICANT
CofO in Progress 2/20/2025 JESUS RODRIGUEZ

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/19/2023 KIRK LINKLATER
Construction near power lines Cleared 6/5/2023 RIDWAN HARDY
Construction within easement Cleared 6/5/2023 RIDWAN HARDY

Contact Information

Contractor Stout Design - Build Inc; Lic. No.: 980007-B       ,
Contractor Stout Design Build Inc; Lic. No.: 980007-B       ,
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/15/2024 Approved ARAM AVEDISIAN
Grounding or Bonding 2/15/2024 Partial Approval ARAM AVEDISIAN
Pool Piping 2/15/2024 Approved ARAM AVEDISIAN
Pre-Gunite 2/15/2024 Approved ARAM AVEDISIAN
Deputy Shotcrete 2/20/2024 No Access for Inspection KENNETH NAGLE
Deck 6/24/2024 Approved ARAM AVEDISIAN
Enclosure/Fence 8/6/2024 Not Ready for Inspection TEMISTOCLES CAAL
Enclosure/Fence 8/29/2024 Corrections Issued JESUS RODRIGUEZ
Enclosure/Fence 9/26/2024 Corrections Issued EVAN COOPER
Final 11/20/2024 Not Ready for Inspection JESUS RODRIGUEZ
Final 12/4/2024 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 1/6/2025 Corrections Issued JESUS RODRIGUEZ
Enclosure/Fence 1/6/2025 Not Ready for Inspection JESUS RODRIGUEZ
Final 1/6/2025 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Final 1/6/2025 Approved JESUS RODRIGUEZ
Rough-Electrical 1/6/2025 Corrections Issued JESUS RODRIGUEZ
Rough-Plumbing 1/6/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 1/23/2025 Approved JESUS RODRIGUEZ
Enclosure/Fence 1/23/2025 Approved JESUS RODRIGUEZ
Final 1/23/2025 Partial Approval JESUS RODRIGUEZ
Grading Pre-Inspection 1/23/2025 Not Ready for Inspection JESUS RODRIGUEZ
Rough-Electrical 1/23/2025 Approved JESUS RODRIGUEZ
Final 2/3/2025 Partial Approval JESUS RODRIGUEZ
Final 2/11/2025 Partial Approval JESUS RODRIGUEZ
Final 2/19/2025 OK to Issue CofO JESUS RODRIGUEZ