88 S FREMONT PL 90005
Certificate Information: 88 S FREMONT PL 90005
- Application / Permit
- 22047-10000-02548
- Plan Check / Job No.
- B22LA25982
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- RESIZE EXISITNG POOL TO 17'x32' AND SPA 12'-6' x 7' USING CITY OF LOS ANGELES STD PLANS 268
- Permit Issued
- Issued on 12/22/2022
- Issuing Office
- Current Status
- CofO Issued on 12/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2022 | AUNG SOE |
| Plan Check Approved | 12/22/2022 | AUNG SOE |
| Issued | 12/22/2022 | APPLICANT |
| CofO in Progress | 12/1/2023 | JEFFREY MEAD |
| No Progress | 12/5/2023 | DEROLD HAUFF |
| CofO in Progress | 12/13/2023 | JOAQUIN GREENOUGH |
| CofO in Progress | 12/13/2023 | JOAQUIN GREENOUGH |
| No Progress | 12/13/2023 | JOAQUIN GREENOUGH |
| CofO in Progress | 12/13/2023 | JOAQUIN GREENOUGH |
| CofO Issued | 12/14/2023 | DEROLD HAUFF |
| Permit Finaled | 12/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Allstate Pools & Spas; Lic. No.: 377945-C53 | 3075 THOUSAND OAKS BLVD THOUSAND OAKS, CA 91362 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 4/20/2023 | Approved | JEFFREY MEAD |
| Deputy Shotcrete | 4/26/2023 | Partial Approval | JEFFREY MEAD |
| Deck | 6/29/2023 | Approved | JEFFREY MEAD |
| Grounding or Bonding | 6/29/2023 | Approved | JEFFREY MEAD |
| Enclosure/Fence | 9/8/2023 | Approved | JEFFREY MEAD |
| Final | 9/29/2023 | Corrections Issued | JEFFREY MEAD |
| Pool Equipment Noise Test | 9/29/2023 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 9/29/2023 | SGSOV Not Ready | JEFFREY MEAD |
| Equipment Noise Level | 10/3/2023 | Not Ready for Inspection | ANDEY CHAPARRO |
| Final | 10/18/2023 | Corrections Issued | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 10/18/2023 | SGSOV Approved | JEFFREY MEAD |
| Equipment Noise Level | 10/19/2023 | Approved | ANDEY CHAPARRO |
| Final | 11/29/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 12/1/2023 | OK to Issue CofO | JEFFREY MEAD |
| Special/Order Compliance | 12/11/2023 | Corrections Issued | JEFFREY MEAD |
| Final | 12/13/2023 | OK to Issue CofO | JOAQUIN GREENOUGH |