3786 S WELLINGTON ROAD 90016

Certificate Information: 3786 S WELLINGTON ROAD 90016

Application / Permit
22047-10000-02539
Plan Check / Job No.
B22LA25925
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 28' X 15' SWIMMING POOL WITH 8' X 8' SPA PER LA CITY STANDARD PLAN #268 AND ENGINEERED DETAIL #220-60.
Permit Issued
Issued on 2/7/2023
Issuing Office
Current Status
CofO Issued on 6/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2022 APPLICANT
Assigned to Plan Check Engineer 12/23/2022 GURUNATH NESARAJAH
Corrections Issued 1/6/2023 MOHAMMAD ESMAILI
Plan Check Approved 1/25/2023 MIROOSH KHACHATOORIAN
Issued 2/7/2023 APPLICANT
CofO in Progress 6/15/2023 ANTHONY EGSON
Permit Finaled 6/18/2023 DEROLD HAUFF
CofO Issued 6/18/2023 DEROLD HAUFF
Permit Finaled 6/18/2023 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 1/4/2023 WALTER RAMIREZ
Construction within easement Cleared 1/4/2023 WALTER RAMIREZ

Contact Information

Contractor Aqua Pool & Spa Construction Inc; Lic. No.: 1046115-C53 7361 ETHEL AVE SUITE 4      NORTH HOLLYWOOD, CA 91605
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 4/6/2023 Approved ANTHONY EGSON
Pre-Gunite 4/6/2023 Approved ANTHONY EGSON
Rough-Electrical 4/6/2023 Approved ANTHONY EGSON
Rough-Plumbing 4/6/2023 Approved ANTHONY EGSON
Deputy Shotcrete 4/25/2023 Approved ANTHONY EGSON
Deck 5/9/2023 Approved ANTHONY EGSON
Grounding or Bonding 5/9/2023 Approved ANTHONY EGSON
Enclosure/Fence 5/22/2023 Approved ANTHONY EGSON
Equipment Noise Level 5/26/2023 Approved JUAN ESCOTO DELGADO
Pool Equipment Noise Test 5/26/2023 Approved JUAN ESCOTO DELGADO
ELECTRICAL-Final 5/30/2023 Approved ANTHONY EGSON
Final 5/30/2023 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 5/30/2023 SGSOV Not Ready ANTHONY EGSON
Final 6/1/2023 Not Ready for Inspection ANTHONY EGSON
Gas Piping or Gas Test 6/1/2023 Approved ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 6/5/2023 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 6/5/2023 SGSOV Approved ANTHONY EGSON
Final 6/15/2023 OK to Issue CofO ANTHONY EGSON