419 N HARPER AVE 90048

Certificate Information: 419 N HARPER AVE 90048

Application / Permit
22047-10000-02514
Plan Check / Job No.
B22LA25633
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New pool 21'-0" x 12'-0" with a maximum depth of 5 feet & New Spa 8'-8" x 5'-0" with a maximum depth of 4'
Permit Issued
Issued on 9/28/2023
Issuing Office
Current Status
CofO Issued on 4/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2022 APPLICANT
Assigned to Plan Check Engineer 12/23/2022 JOE VO
Corrections Issued 12/26/2022 JOE VO
Applicant returned to address corrections 9/5/2023 JOE VO
Applicant returned to address corrections 9/8/2023 DANIEL YIP
Plan Check Approved 9/12/2023 DANIEL YIP
Issued 9/28/2023 APPLICANT
No Progress 3/16/2025 DEROLD HAUFF
CofO in Progress 3/16/2025 DEROLD HAUFF
CofO in Progress 4/10/2025 RAUL BARAJAS
Permit Finaled 4/14/2025 DEROLD HAUFF
CofO Issued 4/14/2025 DEROLD HAUFF
Permit Finaled 4/14/2025 DEROLD HAUFF

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Zhang,, Yao; Lic. No.: NA74572       ,

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/27/2023 Corrections Issued LILIANA PORTILLO
Grounding or Bonding 11/27/2023 Partial Approval LILIANA PORTILLO
Pool Piping 11/27/2023 Partial Approval LILIANA PORTILLO
Pre-Gunite 11/27/2023 Corrections Issued LILIANA PORTILLO
Rough-Electrical 11/27/2023 Partial Approval LILIANA PORTILLO
Rough-Plumbing 11/27/2023 Partial Approval LILIANA PORTILLO
Deputy Shotcrete 1/8/2024 Conditional Approval JOAQUIN GREENOUGH
Gas Piping or Gas Test 9/5/2024 Approved JOSE MACIAS
Grounding or Bonding 9/30/2024 Approved JOSE MACIAS
Enclosure/Fence 10/29/2024 Corrections Issued JOSE MACIAS
Enclosure/Fence 11/7/2024 Approved JOSE MACIAS
Equipment Noise Level 11/7/2024 Approved JUAN ESCOTO DELGADO
Pool Equipment Noise Test 11/7/2024 Approved JUAN ESCOTO DELGADO
Enclosure/Fence 11/13/2024 Approved JOSE MACIAS
Excavation/Setback/Form/Re-Bar 11/13/2024 Approved JOSE MACIAS
Final 11/13/2024 Corrections Issued JOSE MACIAS
Pre-Gunite 11/13/2024 Corrections Issued JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 11/13/2024 SGSOV Approved JOSE MACIAS
Final 11/18/2024 Not Ready for Inspection JOSE MACIAS
Pre-Gunite 11/18/2024 Approved JOSE MACIAS
Final 11/21/2024 Conditional Approval JOSE MACIAS
ELECTRICAL-Final 12/3/2024 Approved JOSE MACIAS
Final 12/3/2024 Conditional Approval JOSE MACIAS
Grading Pre-Inspection 12/3/2024 Approved JOSE MACIAS
Final 12/31/2024 Corrections Issued JOSE MACIAS
Final 4/10/2025 OK to Issue CofO RAUL BARAJAS