15029 W VALLEYHEART DR 91403

Certificate Information: 15029 W VALLEYHEART DR 91403

Application / Permit
22047-10000-02497
Plan Check / Job No.
B22LA24636
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
eplan. New Pool per standard plan 268
Permit Issued
Issued on 4/25/2023
Issuing Office
Current Status
CofO Issued on 1/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2022 APPLICANT
Assigned to Plan Check Engineer 12/13/2022 PRANITA SHAH
Corrections Issued 12/14/2022 PRANITA SHAH
Applicant returned to address corrections 12/27/2022 PRANITA SHAH
Plan Check Approved 1/6/2023 KEVIN MORALES
Issued 4/25/2023 APPLICANT
CofO in Progress 1/8/2024 THOMAS FINNILA
Permit Finaled 1/31/2024 RUBEN SALAS
CofO Issued 1/31/2024 RUBEN SALAS
Permit Finaled 1/31/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/21/2022 FERNANDO GIL
Sewer availability Cleared 12/21/2022 FERNANDO GIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 4/28/2023 Corrections Issued THOMAS FINNILA
Rough-Electrical 4/28/2023 Not Ready for Inspection THOMAS FINNILA
Pre-Gunite 5/4/2023 Corrections Issued THOMAS FINNILA
Gunite 5/8/2023 Conditional Approval THOMAS FINNILA
Grounding or Bonding 5/30/2023 Corrections Issued THOMAS FINNILA
Grounding or Bonding 6/1/2023 Approved CHRISTOPHE COCHRAN
Final 8/18/2023 Corrections Issued THOMAS FINNILA
Pool Equipment Noise Test 8/18/2023 Approved FELIPE PENICHE
Pre-Gunite 8/18/2023 Approved THOMAS FINNILA
Final 8/21/2023 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 9/8/2023 SGSOV Not Ready THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 9/14/2023 Approved THOMAS FINNILA
Final 9/14/2023 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 9/14/2023 SGSOV Approved THOMAS FINNILA
Final 9/20/2023 Corrections Issued THOMAS FINNILA
Final 10/6/2023 Corrections Issued THOMAS FINNILA
Final 10/17/2023 Corrections Issued THOMAS FINNILA
Final 10/26/2023 Partial Approval THOMAS FINNILA
Final 1/5/2024 OK to Issue CofO THOMAS FINNILA