3412 S BEETHOVEN ST 90066
Certificate Information: 3412 S BEETHOVEN ST 90066
- Application / Permit
- 22047-10000-02432
- Plan Check / Job No.
- B22LA24770
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) 24'-5" X 10'-9" POOL WITH 6' X 6' SPA PER STANDARD PLAN #268 AND ENGINEER DETAIL.
- Permit Issued
- Issued on 2/3/2023
- Issuing Office
- Current Status
- CofO Issued on 2/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2022 | ALEC MOUSAKHANIAN |
| Corrections Issued | 12/9/2022 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 1/25/2023 | ALEC MOUSAKHANIAN |
| Issued | 2/3/2023 | APPLICANT |
| CofO in Progress | 2/21/2024 | JESUS RODRIGUEZ |
| Permit Finaled | 2/21/2024 | DANIEL ORRANTE |
| CofO Issued | 2/21/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/21/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Aqua Pool & Spa Construction Inc; Lic. No.: 1046115-C53 | 7361 ETHEL AVE SUITE 4 NORTH HOLLYWOOD, CA 91605 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 2/17/2023 | Not Ready for Inspection | EVAN COOPER |
| Pre-Gunite | 3/9/2023 | Corrections Issued | HERBERT GIRON |
| Pre-Gunite | 3/14/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Pool Piping | 4/11/2023 | Partial Approval | HERBERT GIRON |
| Pre-Gunite | 4/11/2023 | Approved | HERBERT GIRON |
| Special/Order Compliance | 4/11/2023 | Corrections Issued | HERBERT GIRON |
| Deputy Shotcrete | 4/12/2023 | Conditional Approval | JESUS PINEDA |
| Gas Piping or Gas Test | 9/22/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Pool Piping | 9/22/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Gas Piping or Gas Test | 9/28/2023 | Approved | HERBERT GIRON |
| Pool Piping | 9/28/2023 | Approved | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 10/11/2023 | Partial Approval | CLAYTON GRAHAM |
| Grounding or Bonding | 10/24/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Grounding or Bonding | 10/25/2023 | Approved | ARAM AVEDISIAN |
| Enclosure/Fence | 12/1/2023 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 1/23/2024 | Approved | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 1/23/2024 | Approved | JESUS RODRIGUEZ |
| Final | 1/23/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Pool Equipment Noise Test | 1/23/2024 | Approved | JAMES VORHIS |
| SGSOV-Seismic Gas S/O Valve | 1/23/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Final | 2/20/2024 | OK to Issue CofO | JESUS RODRIGUEZ |