135 W VIA MARINA 90292

Certificate Information: 135 W VIA MARINA 90292

Application / Permit
22047-10000-02430
Plan Check / Job No.
B22LA15875
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED SWIMMING POOL INSIDE EXISTING SFD
Permit Issued
Issued on 12/20/2022
Issuing Office
Current Status
CofO Issued on 1/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 CRYSTEL MAALOUF
Corrections Issued 9/15/2022 CRYSTEL MAALOUF
Quality Review Completed 9/19/2022 GARO TELMI
Applicant returned to address corrections 12/7/2022 CRYSTEL MAALOUF
Plan Check Approved 12/20/2022 CRYSTEL MAALOUF
Issued 12/20/2022 APPLICANT
CofO in Progress 1/22/2025 EUGENE CASSIDY
Permit Finaled 1/22/2025 ANSON MAGLASANG
CofO Issued 1/22/2025 ANSON MAGLASANG
Permit Finaled 1/22/2025 ANSON MAGLASANG

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Mack,, Mark; Lic. No.: C17231 427 LINNIE CANAL      VENICE, CA 90291
Contractor Breakform Construction Inc; Lic. No.: 1092047-B 127 ARENA STREET      EL SEGUNDO, CA 90245
Engineer Resnick,, Bruce Daniel; Lic. No.: S3293 1927 PONTIUS AVE      LOS ANGELES, CA 90025

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/26/2023 Corrections Issued JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 7/21/2023 Corrections Issued EVAN COOPER
Grounding or Bonding 7/21/2023 Partial Approval EVAN COOPER
Deputy Shotcrete 7/24/2023 Conditional Approval EVAN COOPER
Grounding or Bonding 8/18/2023 Partial Approval HERBERT GIRON
Pool Piping 8/18/2023 Partial Approval HERBERT GIRON
Pre-Gunite 8/18/2023 Approved HERBERT GIRON
Rough-Electrical 8/18/2023 Partial Approval HERBERT GIRON
Deputy Shotcrete 8/25/2023 Conditional Approval HERBERT GIRON
Pool Piping 10/16/2023 Corrections Issued HERBERT GIRON
Rough-Electrical 10/16/2023 Not Ready for Inspection HERBERT GIRON
Rough-Plumbing 10/16/2023 Corrections Issued HERBERT GIRON
Gas Piping or Gas Test 10/17/2023 Conditional Approval HERBERT GIRON
Pool Piping 10/17/2023 Not Ready for Inspection HERBERT GIRON
Rough-Electrical 10/17/2023 Not Ready for Inspection HERBERT GIRON
Rough-Plumbing 10/17/2023 Not Ready for Inspection HERBERT GIRON
Special/Order Compliance 10/17/2023 Corrections Issued HERBERT GIRON
Pool Piping 10/30/2023 Not Ready for Inspection JESUS RODRIGUEZ
Rough-Electrical 10/30/2023 Not Ready for Inspection JESUS RODRIGUEZ
Rough-Plumbing 10/30/2023 Corrections Issued JESUS RODRIGUEZ
Pool Piping 11/15/2023 Approved HERBERT GIRON
Rough-Electrical 11/15/2023 Approved HERBERT GIRON
Enclosure/Fence 9/18/2024 Corrections Issued HERBERT GIRON
Excavation/Setback/Form/Re-Bar 12/21/2024 No Access for Inspection CHRISTOPHER WILSON
Final 12/21/2024 No Access for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 12/21/2024 SGSOV Not Ready CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 12/24/2024 Approved MICHAEL ALLEN
Final 12/24/2024 Conditional Approval MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 12/24/2024 SGSOV Approved MICHAEL ALLEN
Final 12/27/2024 Corrections Issued MICHAEL ALLEN
Final 1/6/2025 Corrections Issued HERBERT GIRON
Final 1/16/2025 Corrections Issued HERBERT GIRON
Final 1/21/2025 OK to Issue CofO EUGENE CASSIDY