1015 W VICTORIA AVE 90291
Certificate Information: 1015 W VICTORIA AVE 90291
- Application / Permit
- 22047-10000-02301
- Plan Check / Job No.
- B22LA23271
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- eplan Swimming Pool and spa per Standart Plan 268 ** 1 of 2 **
- Permit Issued
- Issued on 4/10/2023
- Issuing Office
- Current Status
- CofO Issued on 2/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2022 | EDWIN ESPIN |
| Corrections Issued | 12/12/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 4/3/2023 | EDWIN ESPIN |
| Plan Check Approved | 4/9/2023 | EDWIN ESPIN |
| Issued | 4/10/2023 | APPLICANT |
| CofO in Progress | 2/8/2024 | HERBERT GIRON |
| Permit Finaled | 2/9/2024 | DANIEL ORRANTE |
| CofO Issued | 2/9/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/9/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| CPC | Cleared | 12/13/2022 | RYAN LY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gunite | 11/14/2023 | Approved | JESUS RODRIGUEZ |
| Gas Piping or Gas Test | 12/12/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Rough-Electrical | 12/12/2023 | Approved | TEMISTOCLES CAAL |
| Rough-Plumbing | 12/12/2023 | Approved | TEMISTOCLES CAAL |
| Gas Piping or Gas Test | 1/3/2024 | Approved | HERBERT GIRON |
| Deck | 1/8/2024 | Approved | HERBERT GIRON |
| Grounding or Bonding | 1/8/2024 | Approved | HERBERT GIRON |
| Special/Order Compliance | 1/8/2024 | Partial Inspection | BEN MOLSTAD |
| Enclosure/Fence | 1/11/2024 | Approved | HERBERT GIRON |
| Pool Equipment Noise Test | 1/30/2024 | Not Ready for Inspection | JAMES VORHIS |
| Excavation/Setback/Form/Re-Bar | 1/31/2024 | Approved | HERBERT GIRON |
| Final | 1/31/2024 | Corrections Issued | HERBERT GIRON |
| Pre-Gunite | 1/31/2024 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 1/31/2024 | SGSOV Not Ready | HERBERT GIRON |
| Pool Equipment Noise Test | 2/2/2024 | Approved | JAMES VORHIS |
| ELECTRICAL-Final | 2/7/2024 | Approved | HERBERT GIRON |
| Final | 2/7/2024 | OK to Issue CofO | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 2/7/2024 | SGSOV Approved | HERBERT GIRON |