956 S WESTCHESTER PL 90019
Certificate Information: 956 S WESTCHESTER PL 90019
- Application / Permit
- 22047-10000-02277
- Plan Check / Job No.
- B22LA22916
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 18'-0" X 38'-0" POOL WITH ATTACHED 10'-0" X 12'-0" SPA - PER LA CITY STANDARD PLAN 268
- Permit Issued
- Issued on 3/16/2023
- Issuing Office
- Current Status
- Issued on 3/16/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 11/14/2022 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 11/30/2022 | DANIEL ABRAMYAN |
| Plan Check Approved | 3/16/2023 | DANIEL ABRAMYAN |
| Issued | 3/16/2023 | APPLICANT |
Permit Application Clearance Information
| HPOZ | Cleared | 11/21/2022 | AMANDA KAINER |
| Construction near power lines | Cleared | 3/14/2023 | TINA MIRANDA |
| Construction within easement | Cleared | 3/14/2023 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: NA67656 | , |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/14/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Rough-Electrical | 11/14/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Grounding or Bonding | 12/18/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Pool Piping | 12/18/2023 | Approved | KATHRYN BUTTERWORTH |
| Pre-Gunite | 12/18/2023 | Approved | KATHRYN BUTTERWORTH |
| Rough-Electrical | 12/18/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Rough-Plumbing | 12/18/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Gas Piping or Gas Test | 1/22/2024 | Partial Inspection | ARTHUR NEGRETE |
| Rough-Plumbing | 1/22/2024 | Partial Inspection | ARTHUR NEGRETE |
| Grounding or Bonding | 3/14/2024 | Approved | ARTHUR NEGRETE |
| Gas Piping or Gas Test | 4/22/2024 | Approved | ARTHUR NEGRETE |
| Rough-Plumbing | 4/22/2024 | Approved | ARTHUR NEGRETE |
| Gunite | 4/23/2024 | Corrections Issued | ARTHUR NEGRETE |
| Excavation/Setback/Form/Re-Bar | 5/10/2024 | Approved | ARTHUR NEGRETE |
| Final | 5/10/2024 | Partial Inspection | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Approved | ARTHUR NEGRETE |