1315 W 61ST ST 90044
Certificate Information: 1315 W 61ST ST 90044
- Application / Permit
- 22047-10000-02272
- Plan Check / Job No.
- B22LA22872
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 29'-7" X 14'-4" SWIMMING POOL W/ 18 IN RBB AND 6'X7' SPA RAISED AND 18 IN W/ WATER FEATURE PER STANDARD PLAN 268 AND SUPPLEMENTAL DETAILS PER ENGINEERING.
- Permit Issued
- Issued on 2/15/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2022 | AUNG SOE |
| Corrections Issued | 11/10/2022 | AUNG SOE |
| Applicant returned to address corrections | 11/28/2022 | JOSEPH RAFOLS |
| Issued | 2/15/2023 | APPLICANT |
| CofO in Progress | 10/19/2023 | JUSTIN HAWLEY |
| Permit Finaled | 11/3/2023 | DEROLD HAUFF |
| CofO Issued | 11/3/2023 | DEROLD HAUFF |
| Permit Finaled | 11/3/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/11/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/28/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Rough-Plumbing | 4/28/2023 | Corrections Issued | ENRIQUE MIRELES |
| Pre-Gunite | 5/2/2023 | Approved | ENRIQUE MIRELES |
| Deck | 7/19/2023 | Approved | ENRIQUE MIRELES |
| Rough-Electrical | 7/19/2023 | Approved | ENRIQUE MIRELES |
| Rough-Plumbing | 7/19/2023 | Approved | ENRIQUE MIRELES |
| Deck | 8/14/2023 | Corrections Issued | ENRIQUE MIRELES |
| Enclosure/Fence | 8/22/2023 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 10/18/2023 | Approved | JUSTIN HAWLEY |
| Final | 10/18/2023 | OK to Issue CofO | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 10/18/2023 | SGSOV Approved | JUSTIN HAWLEY |