4532 N KATHERINE AVE 91423
Certificate Information: 4532 N KATHERINE AVE 91423
- Application / Permit
- 22047-10000-02210
- Plan Check / Job No.
- B22LA22201
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- eplan New 28' x 13'-10" pool with 6' x 6'-5" spa per standard plan 268 and engineering detail 271-60.
- Permit Issued
- Issued on 6/27/2023
- Issuing Office
- Current Status
- CofO Issued on 6/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2022 | LUKE GONZALES |
| Corrections Issued | 11/3/2022 | LUKE GONZALES |
| Applicant returned to address corrections | 5/19/2023 | LUKE GONZALES |
| Applicant returned to address corrections | 6/6/2023 | DANIEL SMILEY |
| Plan Check Approved | 6/27/2023 | DANIEL SMILEY |
| Issued | 6/27/2023 | APPLICANT |
| CofO in Progress | 5/20/2025 | MISAEL ESPARZA |
| Permit Finaled | 6/6/2025 | RUBEN SALAS |
| CofO Issued | 6/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/27/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/29/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Pre-Inspection | 6/29/2023 | Partial Inspection | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 7/28/2023 | Corrections Issued | MISAEL ESPARZA |
| Grounding or Bonding | 7/28/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Rough-Electrical | 7/28/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Rough-Plumbing | 7/28/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 11/28/2023 | Approved | CHRISTOPHER ROJAS |
| Grounding or Bonding | 11/28/2023 | Approved | CHRISTOPHER ROJAS |
| Rough-Plumbing | 11/28/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Gas Piping or Gas Test | 2/22/2024 | Approved | MISAEL ESPARZA |
| Enclosure/Fence | 12/4/2024 | Corrections Issued | MISAEL ESPARZA |
| Enclosure/Fence | 12/27/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 2/5/2025 | Corrections Issued | MISAEL ESPARZA |
| Pre-Gunite | 2/5/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 2/5/2025 | SGSOV Approved | MISAEL ESPARZA |
| Pool Equipment Noise Test | 2/6/2025 | Approved | FELIPE PENICHE |
| Final | 5/19/2025 | OK to Issue CofO | MISAEL ESPARZA |