134 N MCCADDEN PL 90004
Certificate Information: 134 N MCCADDEN PL 90004
- Application / Permit
- 22047-10000-02128
- Plan Check / Job No.
- B22LA21218
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- Eplan: (N) Rectangular Pool with Spa Inside Pool per Standard Plan #268 in Rear of Lot.
- Permit Issued
- Issued on 12/27/2022
- Issuing Office
- Current Status
- CofO Issued on 7/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2022 | DAVID CASTILLO |
| Corrections Issued | 10/26/2022 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 12/6/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 12/20/2022 | DAVID CASTILLO |
| Plan Check Approved | 12/25/2022 | AUNG SOE |
| Issued | 12/27/2022 | APPLICANT |
| CofO in Progress | 6/25/2025 | RONNIE MINDANAO |
| Permit Finaled | 7/5/2025 | DEROLD HAUFF |
| CofO Issued | 7/5/2025 | DEROLD HAUFF |
| Permit Finaled | 7/5/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 11/7/2022 | MIGUEL GAMBOA |
Contact Information
| Contractor | Avanti Pools Inc; Lic. No.: 772516-C53 | 8138 ORION AVE VAN NUYS, CA 91406 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 1/18/2024 | Approved | RICHARD DOCKUS |
| Deputy Shotcrete | 1/24/2024 | Conditional Approval | RICHARD DOCKUS |
| Deck | 11/19/2024 | Approved | RONNIE MINDANAO |
| Gas Piping or Gas Test | 11/19/2024 | Approved | RONNIE MINDANAO |
| Grounding or Bonding | 11/19/2024 | Approved | RONNIE MINDANAO |
| Pool Piping | 11/19/2024 | Approved | RONNIE MINDANAO |
| Rough-Electrical | 11/19/2024 | Approved | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 4/2/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 4/2/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 4/2/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| Enclosure/Fence | 5/6/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 5/6/2025 | Approved | RONNIE MINDANAO |
| Final | 5/6/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 5/6/2025 | SGSOV Approved | RONNIE MINDANAO |
| Enclosure/Fence | 5/13/2025 | Corrections Issued | RONNIE MINDANAO |
| Enclosure/Fence | 5/20/2025 | Approved | RONNIE MINDANAO |
| Final | 5/20/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Gunite | 5/20/2025 | Approved | RONNIE MINDANAO |
| Final | 6/9/2025 | Corrections Issued | RONNIE MINDANAO |
| Equipment Noise Level | 6/10/2025 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| Pool Equipment Noise Test | 6/10/2025 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| Equipment Noise Level | 6/12/2025 | Approved | JUAN ESCOTO DELGADO |
| Final | 6/16/2025 | Corrections Issued | RONNIE MINDANAO |
| Final | 6/24/2025 | OK to Issue CofO | RONNIE MINDANAO |