4224 W PARVA AVE 90027
Certificate Information: 4224 W PARVA AVE 90027
- Application / Permit
- 22047-10000-02102
- Plan Check / Job No.
- B22LA20845
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW SWIMMING POOL/SPA ON PILES WITH CANTILEVER DECK & GLASS RAILINGS
- Permit Issued
- Issued on 10/26/2023
- Issuing Office
- Current Status
- CofO Issued on 3/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | PRANITA SHAH |
| Corrections Issued | 11/1/2022 | PRANITA SHAH |
| Quality Review Completed | 11/18/2022 | KEN GILL |
| Building Plans Picked Up | 12/1/2022 | APPLICANT |
| Applicant returned to address corrections | 12/28/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 2/22/2023 | PRANITA SHAH |
| Plan Check Approved | 9/6/2023 | PRANITA SHAH |
| Issued | 10/26/2023 | APPLICANT |
| CofO in Progress | 3/24/2026 | ENRIQUE MIRELES |
| Permit Finaled | 3/26/2026 | DEROLD HAUFF |
| CofO Issued | 3/26/2026 | DEROLD HAUFF |
| Permit Finaled | 3/26/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/13/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 12/13/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 12/13/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 12/13/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 12/13/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 5/5/2023 | CHRISTOPHER ROCHA |
| Grading Pre-Inspection | Cleared | 9/6/2023 | PRANITA SHAH |
Contact Information
| Contractor | Lozoya Construction; Lic. No.: 1043668-B | 4532 ORCHARD AVE LOS ANGELES, CA 90037 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 11/27/2023 | Partial Approval | JOSEPH MCGARRY |
| Piling/Pier/Caisson | 2/7/2024 | Approved | AMIR NAZARIAN |
| Deputy Other (see comments) | 2/20/2024 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 4/11/2024 | Approved | JOSEPH MCGARRY |
| Gas Piping or Gas Test | 4/11/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Grounding or Bonding | 4/11/2024 | Partial Approval | JOSEPH MCGARRY |
| Pool Piping | 4/11/2024 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 5/7/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 5/22/2025 | Corrections Issued | ENRIQUE MIRELES |
| Pre-Gunite | 5/22/2025 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 5/22/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Final | 6/6/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 3/23/2026 | OK to Issue CofO | ENRIQUE MIRELES |