215 S LUCERNE BLVD 90004
Certificate Information: 215 S LUCERNE BLVD 90004
- Application / Permit
- 22047-10000-02096
- Plan Check / Job No.
- B22LA20796
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan. NEW 20' X 12' SWIMMING POOL PER STANDARD PLAN #268. AUTOMATIC POOL COVER PER ENGINEER DETAIL.
- Permit Issued
- Issued on 12/16/2022
- Issuing Office
- Current Status
- CofO Issued on 8/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | JASON JANGADA |
| Corrections Issued | 10/21/2022 | JASON JANGADA |
| Applicant returned to address corrections | 10/31/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 11/3/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 11/15/2022 | KEVIN MORALES |
| Plan Check Approved | 12/13/2022 | ROSENDO MEDINA |
| Issued | 12/16/2022 | APPLICANT |
| CofO in Progress | 7/17/2023 | STUART CHAPMAN |
| Permit Finaled | 8/13/2023 | DEROLD HAUFF |
| CofO Issued | 8/13/2023 | DEROLD HAUFF |
| Permit Finaled | 8/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 11/4/2022 | DAMIAN GATTO |
| CPC | Cleared | 11/4/2022 | DAMIAN GATTO |
| CPC | Cleared | 11/4/2022 | DAMIAN GATTO |
| HPOZ | Cleared | 11/4/2022 | DAMIAN GATTO |
| Construction near power lines | Cleared | 11/21/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Art'S Pool Plastering & Remodeling; Lic. No.: 906751-C53 | 8504 CEYLON AVENUE PICO RIVERA, CA 90660 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/20/2022 | Approved | RICHARD DOCKUS |
| Gas Piping or Gas Test | 12/20/2022 | Approved | RICHARD DOCKUS |
| Grounding or Bonding | 12/20/2022 | Partial Approval | RICHARD DOCKUS |
| Pre-Gunite | 12/20/2022 | Approved | RICHARD DOCKUS |
| Rough-Electrical | 12/20/2022 | Approved | RICHARD DOCKUS |
| Rough-Plumbing | 12/20/2022 | Approved | RICHARD DOCKUS |
| Deputy Shotcrete | 12/23/2022 | Conditional Approval | RICHARD DOCKUS |
| Deck | 1/24/2023 | Approved | RICHARD DOCKUS |
| Enclosure/Fence | 2/14/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 6/6/2023 | Corrections Issued | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 6/6/2023 | SGSOV Approved | RICHARD DOCKUS |
| Final | 6/16/2023 | Conditional Approval | STUART CHAPMAN |
| Final | 7/12/2023 | OK to Issue CofO | STUART CHAPMAN |