11850 W NORTH PARK AVE 90066
Certificate Information: 11850 W NORTH PARK AVE 90066
- Application / Permit
- 22047-10000-02024
- Plan Check / Job No.
- B22LA20043
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) 14' X 35' POOL WITH 7'-6" X 6' SPA PER LA CITY STD PLAN #270
- Permit Issued
- Issued on 10/19/2022
- Issuing Office
- Current Status
- CofO Issued on 10/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | ALEC MOUSAKHANIAN |
| Corrections Issued | 10/7/2022 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 10/12/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 10/19/2022 | ALEC MOUSAKHANIAN |
| Issued | 10/19/2022 | APPLICANT |
| CofO in Progress | 10/4/2023 | RICHARD STEINBACH |
| Permit Finaled | 10/7/2023 | DANIEL ORRANTE |
| CofO Issued | 10/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 10/17/2022 | RUBEN VASQUEZ |
Contact Information
| Contractor | Mod Luxe Inc; Lic. No.: 1059519-B | , |
| Engineer | Cristescu,, Barbu Dan; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/19/2022 | Approved | JESUS RODRIGUEZ |
| Pre-Gunite | 12/19/2022 | Approved | JESUS RODRIGUEZ |
| Deputy Shotcrete | 1/13/2023 | Conditional Approval | DAVID FEILER |
| Grounding or Bonding | 7/3/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 8/15/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Pool Equipment Noise Test | 8/15/2023 | Approved | JAMES VORHIS |
| Enclosure/Fence | 8/29/2023 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/20/2023 | Approved | HERBERT GIRON |
| Enclosure/Fence | 9/20/2023 | Approved | HERBERT GIRON |
| Final | 9/20/2023 | Conditional Approval | HERBERT GIRON |
| PLUMBING-Final | 9/20/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 9/20/2023 | SGSOV Approved | HERBERT GIRON |
| Final | 10/2/2023 | Partial Approval | JESUS RODRIGUEZ |