5814 E EATON ST 90042
Certificate Information: 5814 E EATON ST 90042
- Application / Permit
- 22047-10000-02019
- Plan Check / Job No.
- B22LA19977
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL WITH SPA USING STANDARD DETAIL #268
- Permit Issued
- Issued on 11/3/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2022 | DANIEL SANJUAN |
| Corrections Issued | 10/4/2022 | DANIEL SANJUAN |
| Applicant returned to address corrections | 10/21/2022 | RAHEL BEYENE |
| Plan Check Approved | 11/3/2022 | FERNANDO FLORES |
| Issued | 11/3/2022 | APPLICANT |
| CofO in Progress | 7/27/2023 | CRAIG VAUGHAN |
| CofO in Progress | 7/27/2023 | CRAIG VAUGHAN |
| Permit Finaled | 8/8/2023 | DEROLD HAUFF |
| CofO Issued | 8/8/2023 | DEROLD HAUFF |
| Permit Finaled | 8/8/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Architectural, & Construction Consulting; Lic. No.: BUS5386 | 101 HANKEN DRIVE KENTFIELD, CA 94904 |
| Contractor | Environmental Landscape Development Inc; Lic. No.: 902300-C53 | 525 W WOODBURY RD ALTADENA, CA 91001 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 11/22/2022 | Approved | AMY COLIN |
| Deck | 12/6/2022 | Approved | SCOTT FINNILA |
| Gas Piping or Gas Test | 12/6/2022 | Approved | SCOTT FINNILA |
| Enclosure/Fence | 3/20/2023 | Corrections Issued | CRAIG VAUGHAN |
| Enclosure/Fence | 3/24/2023 | Corrections Issued | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 5/9/2023 | Approved | CRAIG VAUGHAN |
| Final | 5/9/2023 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/9/2023 | SGSOV Not Ready | CRAIG VAUGHAN |
| Final | 5/16/2023 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/16/2023 | SGSOV Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 5/24/2023 | Approved | CRAIG VAUGHAN |
| Enclosure/Fence | 5/24/2023 | Approved | CRAIG VAUGHAN |
| Final | 5/24/2023 | OK to Issue CofO | CRAIG VAUGHAN |