1017 N DEXTER ST 90042
Certificate Information: 1017 N DEXTER ST 90042
- Application / Permit
- 22047-10000-01959
- Plan Check / Job No.
- B22LA19291
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 16' X 20' SWIMMING POOL WITH 7' X 10' INTERIOR SPA. WORK PER STANDARD PLAN #268 AND ENGINEER DETAILS.
- Permit Issued
- Issued on 12/12/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2022 | PRANITA SHAH |
| Corrections Issued | 10/5/2022 | PRANITA SHAH |
| Plan Check Approved | 11/8/2022 | ROSENDO MEDINA |
| Issued | 12/12/2022 | APPLICANT |
| CofO in Progress | 1/30/2025 | THOMAS LOGRASSO |
| Permit Finaled | 2/2/2025 | DEROLD HAUFF |
| CofO Issued | 2/2/2025 | DEROLD HAUFF |
| Permit Finaled | 2/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/27/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 10/27/2022 | AMAAN MALIK |
| Grading Pre-Inspection | Cleared | 10/31/2022 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mahmoudkhani,, Behnam; Lic. No.: C88488 | 120 W WILSON AVE 1550 GLENDALE, CA 91203 |
| Engineer | Tuchscher,, James Todd; Lic. No.: NA77649 | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/20/2024 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 3/27/2024 | Approved | HAMIK HARTOUNIAN |
| Gas Piping or Gas Test | 3/27/2024 | Approved | HAMIK HARTOUNIAN |
| Rough-Electrical | 3/27/2024 | Approved | HAMIK HARTOUNIAN |
| Rough-Plumbing | 3/27/2024 | Approved | HAMIK HARTOUNIAN |
| Deputy Shotcrete | 3/28/2024 | Corrections Issued | SCOTT FINNILA |
| Grounding or Bonding | 9/24/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Deck | 9/27/2024 | Approved | THOMAS LOGRASSO |
| Grounding or Bonding | 9/27/2024 | Approved | THOMAS LOGRASSO |
| Enclosure/Fence | 10/31/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Enclosure/Fence | 12/16/2024 | Approved | THOMAS LOGRASSO |
| Pool Equipment Noise Test | 1/7/2025 | Approved | ANDEY CHAPARRO |
| Final | 1/14/2025 | Corrections Issued | THOMAS LOGRASSO |
| Pre-Gunite | 1/14/2025 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 1/14/2025 | SGSOV Approved | THOMAS LOGRASSO |
| Final | 1/30/2025 | OK to Issue CofO | THOMAS LOGRASSO |