3025 S MIDVALE AVE 90034
Certificate Information: 3025 S MIDVALE AVE 90034
- Application / Permit
- 22047-10000-01913
- Plan Check / Job No.
- B22LA18694
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePLAN. NEW 28'x10' SWIMMING POOL WITH WATERFALL PER STANDARD PLAN 268 AND ENGR DETAIL.
- Permit Issued
- Issued on 1/25/2023
- Issuing Office
- Current Status
- CofO Issued on 9/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2022 | PRANITA SHAH |
| Corrections Issued | 9/28/2022 | PRANITA SHAH |
| Plan Check Approved | 1/18/2023 | KEVIN MORALES |
| Issued | 1/25/2023 | APPLICANT |
| CofO in Progress | 9/6/2023 | JESUS PINEDA |
| Permit Finaled | 9/8/2023 | DANIEL ORRANTE |
| CofO Issued | 9/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/8/2022 | SAUL GARCIA |
| Sewer availability | Cleared | 10/8/2022 | SAUL GARCIA |
| Miscellaneous | Cleared | 10/22/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2022 | SAUL GARCIA |
| Grading Pre-Inspection | Cleared | 10/26/2022 | KIRK LINKLATER |
| Construction near power lines | Cleared | 1/8/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/27/2023 | Approved | JEREMY TODD |
| Pool Piping | 4/28/2023 | Approved | EVAN COOPER |
| Rough-Electrical | 4/28/2023 | Approved | EVAN COOPER |
| Rough-Plumbing | 4/28/2023 | Approved | EVAN COOPER |
| Grounding or Bonding | 5/23/2023 | Approved | JOHNNY MIRANDA |
| Enclosure/Fence | 6/26/2023 | Corrections Issued | JOHNNY MIRANDA |
| Gunite | 6/26/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Enclosure/Fence | 6/30/2023 | Approved | JOHNNY MIRANDA |
| Pool Equipment Noise Test | 7/25/2023 | Approved | JUAN ESCOTO DELGADO |
| Final | 7/31/2023 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 7/31/2023 | SGSOV Approved | JESUS PINEDA |
| Final | 8/4/2023 | Partial Approval | JESUS PINEDA |
| Final | 9/6/2023 | OK to Issue CofO | JESUS PINEDA |