212 N COPA DE ORO ROAD 90077
Certificate Information: 212 N COPA DE ORO ROAD 90077
- Application / Permit
- 22047-10000-01836
- Plan Check / Job No.
- B22LA16716
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan: (N) pool and spa (38' x 14') to replace (E) pool and spa. (E) pool shell to be removed. Grading for pool under permit #21030-30000-04045. Standard Plan #242. Total of two permits. 2 of 2
- Permit Issued
- Issued on 12/6/2022
- Issuing Office
- Current Status
- CofO Issued on 11/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | TSE MING HUANG |
| Corrections Issued | 10/5/2022 | TSE MING HUANG |
| Quality Review Completed | 10/11/2022 | EUGENE BARBEAU |
| Plan Check Approved | 12/1/2022 | TSE MING HUANG |
| Issued | 12/6/2022 | APPLICANT |
| CofO in Progress | 11/13/2024 | CHRISTOPHER WILSON |
| Permit Finaled | 11/19/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/19/2024 | RICHARD STEINBACH |
| CofO Issued | 11/19/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/1/2022 | TSE MING HUANG |
Contact Information
| Architect | Manion,, Richard M; Lic. No.: C26957 | 11400 WEST OLYMPIC BLVD SUITE 410 LOS ANGELES, CA 90025 |
| Contractor | Utopia Development Inc; Lic. No.: 710612-B | 2371 E 51ST STREET VERNON, CA 90058 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Shniderman,, Jason Bernard; Lic. No.: C20524 | 16000 SHERMAN WAY #234 VAN NUYS, CA 91607 |
| Engineer | Yamini,, Soly; Lic. No.: C33719 | 540 WARNER AVE LOS ANGELES, CA 90024 |
| Geologist | Hollingsworth,, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 2/9/2023 | Corrections Issued | STEPHANIE SWANSON |
| Rough-Plumbing | 2/9/2023 | Approved | STEPHANIE SWANSON |
| Deputy Shotcrete | 2/14/2023 | Conditional Approval | CHRISTOPHER WILSON |
| Grounding or Bonding | 6/7/2023 | Partial Approval | CHRISTOPHER WILSON |
| Enclosure/Fence | 2/8/2024 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 8/12/2024 | Approved | SEAN HAUPT |
| Final | 8/12/2024 | Corrections Issued | SEAN HAUPT |
| Pre-Gunite | 8/12/2024 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 8/12/2024 | SGSOV Approved | SEAN HAUPT |
| Final | 11/12/2024 | OK to Issue CofO | CHRISTOPHER WILSON |