188 N HOMEWOOD ROAD 90049

Certificate Information: 188 N HOMEWOOD ROAD 90049

Application / Permit
22047-10000-01835
Plan Check / Job No.
B22LA17870
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL & SPA PER CITY STANDARD# 268.
Permit Issued
Issued on 2/24/2023
Issuing Office
Current Status
CofO Issued on 3/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2022 APPLICANT
Assigned to Plan Check Engineer 9/6/2022 CRISTINA SALAZAR
Corrections Issued 9/6/2022 CRISTINA SALAZAR
Plan Check Approved 2/24/2023 MINA HABILI
Issued 2/24/2023 APPLICANT
CofO in Progress 3/11/2025 KEVIN SARGSYAN
Permit Finaled 3/12/2025 RICHARD STEINBACH
CofO Issued 3/12/2025 RICHARD STEINBACH
Permit Finaled 3/12/2025 RICHARD STEINBACH

Permit Application Clearance Information

Construction near power lines Cleared 2/22/2023 RIDWAN HARDY

Contact Information

Contractor G3 Urban; Lic. No.: 1040756-B 15235 S WESTERN AVE      GARDENA, CA 90249
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/11/2024 Partial Approval KEVIN SARGSYAN
FLOOD-Proofing Certificate 1/11/2024 Approved KEVIN SARGSYAN
Grounding or Bonding 1/11/2024 Partial Approval KEVIN SARGSYAN
Pre-Gunite 1/11/2024 Corrections Issued KEVIN SARGSYAN
Rough-Electrical 1/11/2024 Not Ready for Inspection KEVIN SARGSYAN
Rough-Plumbing 1/11/2024 Not Ready for Inspection KEVIN SARGSYAN
Pre-Gunite 1/16/2024 Conditional Approval KEVIN SARGSYAN
Rough-Electrical 1/16/2024 Partial Approval KEVIN SARGSYAN
Rough-Plumbing 1/16/2024 Partial Approval KEVIN SARGSYAN
Deputy Shotcrete 1/17/2024 Conditional Approval KEVIN SARGSYAN
Gas Piping or Gas Test 3/20/2024 Approved ARAM AVEDISIAN
Enclosure/Fence 1/30/2025 Corrections Issued KEVIN SARGSYAN
Enclosure/Fence 1/31/2025 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 2/20/2025 Approved ARAM AVEDISIAN
Final 2/20/2025 Corrections Issued ARAM AVEDISIAN
Pre-Gunite 2/20/2025 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 2/20/2025 SGSOV Approved ARAM AVEDISIAN
ELECTRICAL-Final 3/6/2025 Not Ready for Inspection KEVIN SARGSYAN
Pool Equipment Noise Test 3/6/2025 Approved EUSEBIO GUZMAN
Final 3/7/2025 OK to Issue CofO KEVIN SARGSYAN