18807 W EDLEEN DR 91356
Certificate Information: 18807 W EDLEEN DR 91356
- Application / Permit
- 22047-10000-01789
- Plan Check / Job No.
- B22VN12486
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan: (N) SWIMMING POOL & SPA WITH ATTACHED DECK.
- Permit Issued
- Issued on 12/5/2022
- Issuing Office
- Current Status
- CofO Issued on 12/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2022 | DANIEL YIP |
| Corrections Issued | 8/23/2022 | DANIEL YIP |
| Quality Review Completed | 8/24/2022 | GARO TELMI |
| Applicant returned to address corrections | 11/10/2022 | DANIEL YIP |
| Plan Check Approved | 11/18/2022 | DANIEL YIP |
| No Progress | 12/2/2022 | DANIEL YIP |
| Plan Check Approved | 12/2/2022 | DANIEL YIP |
| No Progress | 12/2/2022 | DANIEL YIP |
| Plan Check Approved | 12/2/2022 | DANIEL YIP |
| No Progress | 12/5/2022 | DANIEL YIP |
| Plan Check Approved | 12/5/2022 | DANIEL YIP |
| No Progress | 12/5/2022 | DANIEL YIP |
| Plan Check Approved | 12/5/2022 | DANIEL YIP |
| Issued | 12/5/2022 | APPLICANT |
| CofO in Progress | 11/7/2025 | JOHN KIDWELL |
| No Progress | 11/19/2025 | SEAN WIRCH |
| CofO in Progress | 11/19/2025 | SEAN WIRCH |
| Permit Finaled | 12/13/2025 | MICHAEL PELHAM |
| CofO Issued | 12/13/2025 | MICHAEL PELHAM |
| Permit Finaled | 12/13/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 11/10/2022 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 11/10/2022 | DANIEL YIP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 12/20/2022 | Approved | DAVID SANDOVAL |
| Deputy Grading | 12/21/2022 | Approved | DAVID SANDOVAL |
| Deputy Other (see comments) | 12/22/2022 | Approved | DAVID SANDOVAL |
| Piling/Pier/Caisson | 12/22/2022 | Partial Approval | DAVID SANDOVAL |
| Deputy Grading | 1/3/2023 | Approved | DAVID SANDOVAL |
| Deputy Grading | 1/4/2023 | Conditional Approval | DAVID SANDOVAL |
| Deputy Grading | 1/5/2023 | Conditional Approval | DAVID SANDOVAL |
| Deputy Grading | 1/6/2023 | Conditional Approval | DAVID SANDOVAL |
| Deputy Grading | 1/9/2023 | Approved | DAVID SANDOVAL |
| Deputy Grading | 1/9/2023 | Conditional Approval | JUSTIN HAWLEY |
| Deputy Other (see comments) | 1/10/2023 | Conditional Approval | DAVID SANDOVAL |
| Piling/Pier/Caisson | 1/17/2023 | Partial Approval | DAVID SANDOVAL |
| Deputy Grading | 1/18/2023 | Conditional Approval | DAVID SANDOVAL |
| Deputy Drilled-In Anchors | 1/23/2023 | Conditional Approval | DAVID SANDOVAL |
| Deputy Grading | 2/14/2023 | Approved | DAVID SANDOVAL |
| Deputy Grading | 2/15/2023 | Approved | DAVID SANDOVAL |
| Deputy Grading | 2/16/2023 | Approved | DAVID SANDOVAL |
| Deputy Grading | 2/21/2023 | Approved | DAVID SANDOVAL |
| Deputy Grading | 2/22/2023 | Approved | DAVID SANDOVAL |
| Piling/Pier/Caisson | 3/8/2023 | Partial Approval | DAVID SANDOVAL |
| Deputy Other (see comments) | 3/9/2023 | Approved | DAVID SANDOVAL |
| Deputy Grading | 3/23/2023 | Approved | DAVID SANDOVAL |
| Deputy Grading | 3/28/2023 | Approved | DAVID SANDOVAL |
| Deputy Other (see comments) | 4/17/2023 | Approved | DAVID SANDOVAL |
| Piling/Pier/Caisson | 11/7/2023 | Corrections Issued | SEAN HAUPT |
| Piling/Pier/Caisson | 11/9/2023 | Corrections Issued | SEAN HAUPT |
| Piling/Pier/Caisson | 11/15/2023 | Partial Approval | SEAN HAUPT |
| Deputy Other (see comments) | 11/16/2023 | Approved | SEAN HAUPT |
| Pre-Gunite | 1/4/2024 | Approved | SEAN HAUPT |
| Rough-Electrical | 1/4/2024 | Approved | SEAN HAUPT |
| Rough-Plumbing | 1/4/2024 | Partial Approval | SEAN HAUPT |
| Deputy Shotcrete | 1/12/2024 | Approved | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 4/10/2024 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 5/1/2024 | Approved | JOHN KIDWELL |
| Piling/Pier/Caisson | 6/13/2024 | Corrections Issued | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 7/2/2024 | Approved | JOHN KIDWELL |
| Grounding or Bonding | 11/4/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Enclosure/Fence | 12/10/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Enclosure/Fence | 12/23/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Grounding or Bonding | 12/23/2024 | Approved | JOHN KIDWELL |
| Enclosure/Fence | 1/29/2025 | Approved | JOHN KIDWELL |
| Final | 9/16/2025 | OK to Issue CofO | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 9/16/2025 | SGSOV Approved | JOHN KIDWELL |