868 N NORMAN PL 90049
Certificate Information: 868 N NORMAN PL 90049
- Application / Permit
- 22047-10000-01773
- Plan Check / Job No.
- B22LA17197
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- STANDARD POOL #268 NEW POOL (30' X 14')
- Permit Issued
- Issued on 9/26/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2022 | RAHEL BEYENE |
| Corrections Issued | 8/26/2022 | RAHEL BEYENE |
| Issued | 9/26/2022 | APPLICANT |
| CofO in Progress | 7/12/2023 | CARLOS MATAMOROS |
| Permit Finaled | 7/14/2023 | DANIEL ORRANTE |
| CofO Issued | 7/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Watercourse | Cleared | 9/20/2022 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2022 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Intex Design And Construction Inc; Lic. No.: 981718-C53 | 15021 VENTURA BLVD STE 520 SHERMAN OAKS, CA 91403 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/1/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Piping or Gas Test | 3/16/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Rough-Electrical | 3/16/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Piping or Gas Test | 3/20/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Pool Piping | 3/20/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Rough-Electrical | 3/20/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Rough-Plumbing | 3/20/2023 | Corrections Issued | STEPHANIE SWANSON |
| Pre-Gunite | 3/24/2023 | Approved | JESUS RODRIGUEZ |
| Deputy Shotcrete | 3/30/2023 | Conditional Approval | MICHAEL PELHAM |
| Enclosure/Fence | 5/23/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pre-Inspection | 5/23/2023 | Partial Approval | CARLOS MATAMOROS |
| Enclosure/Fence | 6/2/2023 | Approved | CARLOS MATAMOROS |
| Equipment Noise Level | 6/8/2023 | Approved | OSCAR SALGADO |
| ELECTRICAL-Final | 7/7/2023 | Approved | CARLOS MATAMOROS |
| Final | 7/7/2023 | OK to Issue CofO | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 7/7/2023 | SGSOV Approved | CARLOS MATAMOROS |