19841 W HENSHAW ST 91364
Certificate Information: 19841 W HENSHAW ST 91364
- Application / Permit
- 22047-10000-01644
- Plan Check / Job No.
- B22VN12093
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- EPLAN. (N) POOL (POOL B) PER STANDARD PLAN
- Permit Issued
- Issued on 8/27/2022
- Issuing Office
- Current Status
- CofO Issued on 3/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2022 | FERNANDO FLORES |
| Corrections Issued | 8/9/2022 | FERNANDO FLORES |
| Applicant returned to address corrections | 8/11/2022 | FERNANDO FLORES |
| Plan Check Approved | 8/27/2022 | FERNANDO FLORES |
| Issued | 8/27/2022 | APPLICANT |
| CofO in Progress | 3/22/2023 | DAVID SANDOVAL |
| Permit Finaled | 3/22/2023 | JOHN JANSON |
| CofO Issued | 3/22/2023 | JOHN JANSON |
| Permit Finaled | 3/22/2023 | JOHN JANSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Green Works Construction & Design Inc; Lic. No.: 936962-B | , |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 10/13/2022 | Approved | DAVID SANDOVAL |
| Pre-Gunite | 10/13/2022 | Approved | DAVID SANDOVAL |
| Rough-Electrical | 10/13/2022 | Approved | DAVID SANDOVAL |
| Rough-Plumbing | 10/13/2022 | Approved | DAVID SANDOVAL |
| Deputy Shotcrete | 10/18/2022 | Conditional Approval | MORRIS JACKSON |
| Grounding or Bonding | 11/18/2022 | No Access for Inspection | DAVID SANDOVAL |
| Special/Order Compliance | 11/18/2022 | Partial Inspection | JESUS PINEDA |
| Deck | 11/28/2022 | Approved | DAVID SANDOVAL |
| Special/Order Compliance | 11/28/2022 | Partial Inspection | JESUS PINEDA |
| Enclosure/Fence | 1/19/2023 | Approved | DAVID SANDOVAL |
| Pool Equipment Noise Test | 1/25/2023 | Approved | ALFREDO FLORES |
| Equipment Noise Level | 1/26/2023 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 2/8/2023 | Approved | DAVID SANDOVAL |
| Final | 2/8/2023 | Corrections Issued | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 2/8/2023 | SGSOV Approved | DAVID SANDOVAL |
| Final | 2/28/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 3/22/2023 | OK to Issue CofO | DAVID SANDOVAL |