520 N VIA DE LA PAZ 90272

Certificate Information: 520 N VIA DE LA PAZ 90272

Application / Permit
22047-10000-01566
Plan Check / Job No.
B22LA15127
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
ePlan: (N) 12'4" X 32'4" SWIMMING POOL AND 7'2" X 8'4" SPA PER LACITY STANDARD PLAN #265 AND SUPPLEMENTAL DETAILS PER ENGINEER.
Permit Issued
Issued on 9/29/2023
Issuing Office
Current Status
CofO in Progress on 10/29/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/3/2022 APPLICANT
Assigned to Plan Check Engineer 8/10/2022 OMAR GARNICA
Corrections Issued 8/11/2022 OMAR GARNICA
Plan Check Approved 9/29/2023 OMAR GARNICA
Issued 9/29/2023 APPLICANT
CofO in Progress 10/29/2024 EVAN COOPER
CofO in Progress 11/15/2024 EVAN COOPER

Permit Application Clearance Information

Coastal Zone Cleared 11/1/2022 DANIEL CORONADO
Construction near power lines Cleared 9/9/2023 TINA MIRANDA
Construction within easement Cleared 9/9/2023 TINA MIRANDA

Contact Information

Contractor Shinn Construction; Lic. No.: 1054419-B       ,
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 11/17/2023 Corrections Issued EVAN COOPER
Pre-Gunite 1/18/2024 Conditional Approval EVAN COOPER
Deputy Shotcrete 1/19/2024 No Access for Inspection KENNETH NAGLE
Pre-Gunite 1/19/2024 Approved KENNETH NAGLE
ELECTRICAL-Final 9/9/2024 Not Ready for Inspection EVAN COOPER
Enclosure/Fence 9/9/2024 Corrections Issued EVAN COOPER
Excavation/Setback/Form/Re-Bar 9/9/2024 Approved EVAN COOPER
Final 9/9/2024 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 9/9/2024 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/9/2024 SGSOV Approved EVAN COOPER
Pool Equipment Noise Test 9/26/2024 Not Ready for Inspection EUSEBIO GUZMAN
Equipment Noise Level 10/1/2024 Approved EUSEBIO GUZMAN
Final 10/2/2024 Conditional Approval EVAN COOPER
Final 10/29/2024 Conditional Approval EVAN COOPER
Special/Order Compliance 11/18/2024 Corrections Issued EVAN COOPER