661 S MORENO AVE 90049
Certificate Information: 661 S MORENO AVE 90049
- Application / Permit
- 22047-10000-01561
- Plan Check / Job No.
- B22LA15075
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED POOL. 4 OF 6
- Permit Issued
- Issued on 10/12/2023
- Issuing Office
- Current Status
- Issued on 10/12/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | MICHAEL LOPEZ |
| Corrections Issued | 8/26/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 8/31/2022 | KEN GILL |
| Building Plans Picked Up | 9/6/2022 | APPLICANT |
| Applicant returned to address corrections | 10/21/2022 | TU HUA |
| Applicant returned to address corrections | 2/14/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 7/10/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 7/26/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 10/4/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 10/12/2023 | MICHAEL LOPEZ |
| Issued | 10/12/2023 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Abbott R T Construction Inc; Lic. No.: 746685-B | 543 COUNTRY CLUB DRIVE BOX 205 SIMI VALLEY, CA 93065 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/13/2025 | Corrections Issued | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 8/19/2025 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 8/19/2025 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 8/19/2025 | Approved | ARAM AVEDISIAN |
| Pre-Gunite | 8/19/2025 | Approved | ARAM AVEDISIAN |
| Gunite | 9/2/2025 | Approved | MICHAEL ALLEN |
| Gas Piping or Gas Test | 4/7/2026 | Approved | RYAN SALAZAR |
| Pool Piping | 4/7/2026 | Approved | RYAN SALAZAR |
| Rough-Electrical | 4/7/2026 | Approved | RYAN SALAZAR |
| Rough-Plumbing | 4/7/2026 | Approved | RYAN SALAZAR |