3130 S MOUNTAIN VIEW AVE 90066
Certificate Information: 3130 S MOUNTAIN VIEW AVE 90066
- Application / Permit
- 22047-10000-01481
- Plan Check / Job No.
- B22LA14221
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan New pool and spa
- Permit Issued
- Issued on 9/20/2022
- Issuing Office
- Current Status
- CofO Issued on 5/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | JAD BASMA |
| Corrections Issued | 8/25/2022 | JAD BASMA |
| Quality Review Completed | 9/2/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 9/20/2022 | JAD BASMA |
| Issued | 9/20/2022 | APPLICANT |
| CofO in Progress | 5/30/2024 | JESUS PINEDA |
| Permit Finaled | 5/31/2024 | DANIEL ORRANTE |
| CofO Issued | 5/31/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/31/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/14/2022 | JAD BASMA |
Contact Information
| Contractor | Martinko Construction Inc; Lic. No.: 990964-B | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 6/14/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Pre-Gunite | 6/15/2023 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Shotcrete | 6/20/2023 | Conditional Approval | DAVID FEILER |
| Gas Piping or Gas Test | 7/17/2023 | Approved | JESUS PINEDA |
| Grounding or Bonding | 7/17/2023 | Approved | JESUS PINEDA |
| Grounding or Bonding | 8/14/2023 | Approved | JESUS PINEDA |
| Enclosure/Fence | 12/1/2023 | Approved | JESUS PINEDA |
| Pool Equipment Noise Test | 5/2/2024 | Approved | EUSEBIO GUZMAN |
| Excavation/Setback/Form/Re-Bar | 5/9/2024 | Approved | JESUS PINEDA |
| Final | 5/9/2024 | Corrections Issued | JESUS PINEDA |
| Pre-Gunite | 5/9/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 5/9/2024 | SGSOV Approved | JESUS PINEDA |
| Final | 5/30/2024 | OK to Issue CofO | JESUS PINEDA |