1834 N WESTERLY TER 90026
Certificate Information: 1834 N WESTERLY TER 90026
- Application / Permit
- 22047-10000-01443
- Plan Check / Job No.
- B22LA13781
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL AND SPA PER ENGINEER'S DESIGN
- Permit Issued
- Issued on 4/22/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | SUNMIN LEE |
| Corrections Issued | 7/23/2022 | SUNMIN LEE |
| Quality Review Completed | 8/4/2022 | JOHN FRANCIA |
| Applicant returned to address corrections | 4/10/2023 | SUNMIN LEE |
| Plan Check Approved | 4/16/2024 | SUNMIN LEE |
| Issued | 4/22/2024 | APPLICANT |
| CofO in Progress | 8/26/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 8/28/2025 | DEROLD HAUFF |
| CofO Issued | 8/28/2025 | DEROLD HAUFF |
| Permit Finaled | 8/28/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/2/2023 | SUNMIN LEE |
Contact Information
| Contractor | Caire John Construction Inc; Lic. No.: 626684-B | 2028 LOMBARDY DR LA CANADA, CA 91011 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Geologist | Triebold,, Mark John; Lic. No.: EG1796 | 6906 QUITO COURT CAMARILLO, CA 93012 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 9/18/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Pre-Gunite | 9/24/2024 | Approved | HAMIK HARTOUNIAN |
| Deputy Other (see comments) | 10/1/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| Deputy Shotcrete | 10/2/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| Rough-Electrical | 12/3/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Deck | 12/10/2024 | Approved | HAMIK HARTOUNIAN |
| Enclosure/Fence | 1/17/2025 | Approved | OSVALDO PARAMO |
| Pool Equipment Noise Test | 2/20/2025 | Approved | JUAN ESCOTO DELGADO |
| Excavation/Setback/Form/Re-Bar | 2/25/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 2/25/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/25/2025 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Final | 3/18/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2025 | SGSOV No Gas | HAMIK HARTOUNIAN |
| Final | 3/26/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 6/12/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 8/20/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Final | 8/26/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |