1704 W STONE CANYON ROAD 90077

Certificate Information: 1704 W STONE CANYON ROAD 90077

Application / Permit
22047-10000-01369
Plan Check / Job No.
B22LA12842
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
ePlan: (N) ELEVATED POOL AND SPA
Permit Issued
Issued on 2/13/2023
Issuing Office
Current Status
CofO Issued on 10/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/5/2022 APPLICANT
Assigned to Plan Check Engineer 7/15/2022 DANIEL YIP
Corrections Issued 7/25/2022 DANIEL YIP
Quality Review Completed 7/25/2022 GARO TELMI
Plan Check Approved 8/23/2022 DANIEL YIP
Issued 2/13/2023 APPLICANT
Permit Finaled 10/8/2024 RICHARD STEINBACH
CofO Issued 10/8/2024 RICHARD STEINBACH
Permit Finaled 10/8/2024 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/23/2022 DANIEL YIP

Contact Information

Architect , ; Lic. No.: C34216 4701 GLENALBYN DR      LOS ANGELES, CA 90065
Contractor Select Contractors Inc; Lic. No.: 772406-B       ,
Engineer Behshid,, Farshid; Lic. No.: NA4585       ,
Engineer Behshid,, Farshid; Lic. No.: S4585 10866 WIMER COUNTRY ROAD      SUNLAND, CA 91040

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 4/14/2023 Conditional Approval MICHAEL PELHAM
Deputy Grading 4/17/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 5/2/2023 Corrections Issued CHRISTOPHER WILSON
Piling/Pier/Caisson 5/2/2023 Partial Approval CHRISTOPHER WILSON
Deputy Grading 5/23/2023 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/23/2023 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/29/2023 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/11/2023 Partial Approval CHRISTOPHER WILSON
Final 11/2/2023 Corrections Issued CHRISTOPHER WILSON
Grounding or Bonding 11/2/2023 Not Ready for Inspection CHRISTOPHER WILSON
Pool Piping 11/2/2023 Corrections Issued CHRISTOPHER WILSON
Pre-Gunite 11/2/2023 Corrections Issued CHRISTOPHER WILSON
Rough-Electrical 11/2/2023 Not Ready for Inspection CHRISTOPHER WILSON
Grounding or Bonding 11/8/2023 Partial Approval CHRISTOPHER WILSON
Pool Piping 11/8/2023 Approved CHRISTOPHER WILSON
Pre-Gunite 11/8/2023 Approved CHRISTOPHER WILSON
Rough-Electrical 11/8/2023 Partial Approval CHRISTOPHER WILSON
Rough-Plumbing 11/8/2023 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 11/16/2023 Conditional Approval MICHAEL PELHAM
Deck 3/29/2024 Not Ready for Inspection CHRISTOPHER WILSON
Grounding or Bonding 3/29/2024 Corrections Issued CHRISTOPHER WILSON
Grounding or Bonding 4/2/2024 Partial Approval CHRISTOPHER WILSON
Enclosure/Fence 6/17/2024 Not Ready for Inspection CHRISTOPHER WILSON
Enclosure/Fence 7/12/2024 Approved CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/13/2024 Approved CHRISTOPHER WILSON
Final 9/13/2024 Not Ready for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 9/13/2024 SGSOV Approved CHRISTOPHER WILSON
Final 9/19/2024 Corrections Issued CHRISTOPHER WILSON
Final 9/20/2024 Conditional Approval CHRISTOPHER WILSON
PLUMBING-Final 9/20/2024 Approved CHRISTOPHER WILSON