942 E INDIANA AVE 90291
Certificate Information: 942 E INDIANA AVE 90291
- Application / Permit
- 22047-10000-01280
- Plan Check / Job No.
- B22LA11837
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- eplan Install new pool. Install filtration and heating equipment. Install gas & electric to equipment and light. PER STANDARD PLAN
- Permit Issued
- Issued on 8/12/2022
- Issuing Office
- Current Status
- CofO Issued on 3/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | KHUONG TRUONG |
| Plan Check Approved | 8/5/2022 | KHUONG TRUONG |
| Issued | 8/12/2022 | APPLICANT |
| CofO in Progress | 3/21/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 3/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/24/2023 | DANIEL ORRANTE |
| CofO Issued | 3/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Swimming Pool & Spa Surgeon; Lic. No.: 466383-C53 | 4685 RUNWAY STREET UNIT P SIMI VALLEY, CA 93063 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 11/4/2022 | Corrections Issued | DAVID FEILER |
| Pre-Gunite | 11/4/2022 | Approved | DAVID FEILER |
| Gas Piping or Gas Test | 11/7/2022 | Approved | DAVID FEILER |
| Grounding or Bonding | 12/8/2022 | Partial Approval | EVAN COOPER |
| Enclosure/Fence | 2/15/2023 | Approved | EVAN COOPER |
| Equipment Noise Level | 2/28/2023 | Approved | JAMES VORHIS |
| Excavation/Setback/Form/Re-Bar | 3/6/2023 | Approved | HERBERT GIRON |
| Final | 3/6/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 3/6/2023 | SGSOV Not Ready | HERBERT GIRON |
| Final | 3/9/2023 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 3/9/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 3/21/2023 | Approved | JESUS RODRIGUEZ |
| Final | 3/21/2023 | OK to Issue CofO | JESUS RODRIGUEZ |