19114 W CALVERT ST 91335

Certificate Information: 19114 W CALVERT ST 91335

Application / Permit
22047-10000-01268
Plan Check / Job No.
B22LA11776
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 29'-0" x 14'-0" POOL AND 8'-0" x 7'-9" SPA WITH BAJA PER CITY STD. PLAN #268 AND ENGINEERING DETAILS
Permit Issued
Issued on 8/17/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2022 APPLICANT
Assigned to Plan Check Engineer 6/17/2022 JOSEPH RAFOLS
Corrections Issued 6/17/2022 JOSEPH RAFOLS
Issued 8/17/2022 APPLICANT
CofO in Progress 7/5/2024 JON MCHUGH
Permit Finaled 8/2/2024 JOHN JANSON
CofO Issued 8/2/2024 JOHN JANSON
Permit Finaled 8/2/2024 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 8/7/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/11/2022 Not Ready for Inspection DAVID SANDOVAL
Gas Piping or Gas Test 10/11/2022 Approved DAVID SANDOVAL
Grounding or Bonding 10/11/2022 Partial Approval DAVID SANDOVAL
Pool Piping 10/11/2022 Not Ready for Inspection DAVID SANDOVAL
Pre-Gunite 10/11/2022 Corrections Issued DAVID SANDOVAL
Rough-Electrical 10/11/2022 Approved DAVID SANDOVAL
Rough-Plumbing 10/11/2022 Approved DAVID SANDOVAL
Gas Piping or Gas Test 10/17/2022 Approved DAVID SCANTLIN
Pool Piping 10/17/2022 Approved DAVID SCANTLIN
Pre-Gunite 10/17/2022 Approved DAVID SCANTLIN
Rough-Electrical 10/17/2022 Approved DAVID SCANTLIN
Rough-Plumbing 10/17/2022 Approved DAVID SCANTLIN
Grounding or Bonding 1/5/2023 Corrections Issued SEAN HAUPT
Gunite 1/5/2023 Corrections Issued SEAN HAUPT
Special/Order Compliance 1/5/2023 Partial Inspection MORRIS JACKSON
Deputy Shotcrete 1/6/2023 No Access for Inspection JON MCHUGH
Deck 1/23/2023 Approved SEAN HAUPT
Deputy Shotcrete 1/23/2023 Partial Approval SEAN HAUPT
Grounding or Bonding 1/24/2023 Approved SEAN HAUPT
Enclosure/Fence 5/16/2023 Corrections Issued JON MCHUGH
Enclosure/Fence 5/23/2023 Approved MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 6/3/2024 Approved JON MCHUGH
Final 6/3/2024 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 6/3/2024 SGSOV Approved JON MCHUGH
Equipment Noise Level 6/5/2024 Approved ALFREDO FLORES
Final 7/3/2024 Corrections Issued JON MCHUGH
Final 7/5/2024 OK to Issue CofO JON MCHUGH
Enclosure/Fence 7/30/2024 Approved MORRIS JACKSON