10950 W VERANO ROAD 90077

Certificate Information: 10950 W VERANO ROAD 90077

Application / Permit
22047-10000-01229
Plan Check / Job No.
B22LA11485
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL WITH SPA
Permit Issued
Issued on 1/20/2023
Issuing Office
Current Status
CofO Issued on 2/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 CARLOS MONTES
Corrections Issued 7/20/2022 CARLOS MONTES
Quality Review Completed 7/21/2022 GARO TELMI
Applicant returned to address corrections 8/5/2022 CARLOS MONTES
Applicant returned to address corrections 9/2/2022 CARLOS MONTES
Applicant returned to address corrections 11/17/2022 CARLOS MONTES
Applicant returned to address corrections 12/14/2022 CARLOS MONTES
Plan Check Approved 1/20/2023 CARLOS MONTES
Issued 1/20/2023 APPLICANT
CofO in Progress 2/14/2025 CARLOS MATAMOROS
Permit Finaled 2/20/2025 RICHARD STEINBACH
CofO Issued 2/20/2025 RICHARD STEINBACH
Permit Finaled 2/20/2025 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/20/2023 CARLOS MONTES

Contact Information

Contractor Agam Pool And Spa Inc; Lic. No.: 993464-C53       ,
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Geologist Bovenizer,, Ernest; Lic. No.: EG2515 7622 GODDARD AVENUE      LOS ANGELES, CA 90045

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 2/16/2024 Partial Approval CHRISTOPHER WILSON
Grounding or Bonding 2/16/2024 Partial Approval CHRISTOPHER WILSON
Pool Piping 2/16/2024 Approved CHRISTOPHER WILSON
Pre-Gunite 2/16/2024 Approved CHRISTOPHER WILSON
Rough-Electrical 2/16/2024 Partial Approval CHRISTOPHER WILSON
Rough-Plumbing 2/16/2024 Partial Approval CHRISTOPHER WILSON
Deck 9/10/2024 Approved CHRISTOPHER WILSON
Grounding or Bonding 9/10/2024 Partial Approval CHRISTOPHER WILSON
Enclosure/Fence 11/7/2024 Not Ready for Inspection CHRISTOPHER WILSON
Enclosure/Fence 11/19/2024 Not Ready for Inspection CHRISTOPHER WILSON
Enclosure/Fence 11/22/2024 Approved CHRISTOPHER WILSON
Pool Equipment Noise Test 1/30/2025 Approved JUAN ESCOTO DELGADO
Excavation/Setback/Form/Re-Bar 2/10/2025 Approved MICHAEL PELHAM
Final 2/10/2025 Corrections Issued MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 2/10/2025 SGSOV Approved MICHAEL PELHAM
ELECTRICAL-Final 2/13/2025 Approved CARLOS MATAMOROS
Final 2/13/2025 OK to Issue CofO CARLOS MATAMOROS