7021 W 83RD ST 90045
Certificate Information: 7021 W 83RD ST 90045
- Application / Permit
- 22047-10000-01115
- Plan Check / Job No.
- B22LA10280
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- *EPLAN* NEW POOL (OUTSIDE: 28' X 13'-8.5" / INSIDE: 23' X 11'-8") PER STD PLAN 268 SHEET 100 DETAIL 271-60, 551, AND 672.
- Permit Issued
- Issued on 8/5/2022
- Issuing Office
- Current Status
- CofO Issued on 4/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2022 | VIVIAN LAO |
| Corrections Issued | 6/1/2022 | VIVIAN LAO |
| Plan Check Approved | 8/3/2022 | VIVIAN LAO |
| Issued | 8/5/2022 | APPLICANT |
| CofO in Progress | 4/3/2023 | BOBBY KEY |
| Permit Finaled | 4/3/2023 | DANIEL ORRANTE |
| CofO Issued | 4/3/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/3/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Pomer Construction Inc; Lic. No.: 908354-B | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/12/2022 | Approved | BOBBY KEY |
| Grounding or Bonding | 10/12/2022 | Approved | BOBBY KEY |
| Pool Piping | 10/12/2022 | Corrections Issued | BOBBY KEY |
| Pre-Gunite | 10/12/2022 | Not Ready for Inspection | BOBBY KEY |
| Gas Piping or Gas Test | 10/18/2022 | Approved | BOBBY KEY |
| Grounding or Bonding | 10/18/2022 | Partial Approval | BOBBY KEY |
| Pool Piping | 10/18/2022 | Approved | BOBBY KEY |
| Pre-Gunite | 10/18/2022 | Approved | BOBBY KEY |
| Deputy Other (see comments) | 10/26/2022 | Conditional Approval | BOBBY KEY |
| Deputy Shotcrete | 10/26/2022 | Conditional Approval | BOBBY KEY |
| Deck | 11/22/2022 | Approved | BOBBY KEY |
| Enclosure/Fence | 2/24/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Pool/Spa Cover | 2/24/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Enclosure/Fence | 3/9/2023 | Approved | BOBBY KEY |
| Pool/Spa Cover | 3/9/2023 | Approved | BOBBY KEY |
| Equipment Noise Level | 3/17/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Final | 3/20/2023 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/20/2023 | SGSOV Approved | BOBBY KEY |
| Final | 4/3/2023 | OK to Issue CofO | BOBBY KEY |